Projects and operators

Data centre projects

27 published campus, phase and building records. Each figure keeps its own metric class, stage and source. Filters update the address bar so you can share a view.

Also see operators and cloud regions. A cloud region is not a campus.

27 of 27 projects

Data centre projects
ProjectCountryStageLevelKey reported figureOperator, developer or ownerLatest change
Abilene AI campus at Lancium Clean Campus (Stargate Abilene, Texas)United States
Texas
Under constructioncampus1.2 GWAnnouncedCrusoe, Lancium18 Mar 2025: Phase two construction started (six buildings)
Abilene AI campus phase 1 (two buildings)
Part of Abilene AI campus at Lancium Clean Campus (Stargate Abilene, Texas)
United States
Texas
Under constructionphaseat least 200 MWUnder constructionCrusoe18 Mar 2025: Phase two construction started (six buildings)
AirTrunk JHB1 (Johor Bahru)Malaysia
Johor
Operatingcampusat least 150 MWDesign or ultimate capacityAirTrunknot disclosed
AirTrunk JHB2 (Iskandar Puteri, Johor)Malaysia
Johor
Announcedcampusat least 270 MWAnnouncedAirTrunk12 Feb 2025: Announced by AirTrunk
DataVolt Oxagon AI data centre campus (NEOM)Saudi Arabia
Tabuk Province (NEOM)
Under constructioncampusnot disclosedDataVolt31 Aug 2026: Construction started on first phase
DataVolt Oxagon phase 1 (360 MW, incl. 100 MW with HUMAIN)
Part of DataVolt Oxagon AI data centre campus (NEOM)
Saudi Arabia
Tabuk Province (NEOM)
Under constructionphasenot disclosedDataVolt, HUMAIN31 Aug 2026: Construction started on first phase
Digital Realty DC-CFA2 data centre (Jurong Island, Singapore)Singapore
Jurong Island
Provisional capacity allocationproject50 MWProvisional allocationDigital Realty21 Aug 2026: EDB and IMDA provisionally allocated 50 MW each to Digital Realty, Equinix, Keppel Data Centres and STT GDC under the second Data Centre Call for Application. Winners committed to at least 50% green energy pathways, liquid cooling, Green Mark Platinum and efficient IT.
Equinix DB7x (Blanchardstown, Dublin)Ireland
Fingal, Dublin
Under constructionbuildingUSD 92 millionInvestmentEquinix20 Mar 2026: Construction started
Equinix DC-CFA2 data centre (Jurong Island, Singapore)Singapore
Jurong Island
Provisional capacity allocationproject50 MWProvisional allocationEquinix21 Aug 2026: EDB and IMDA provisionally allocated 50 MW each to Digital Realty, Equinix, Keppel Data Centres and STT GDC under the second Data Centre Call for Application. Winners committed to at least 50% green energy pathways, liquid cooling, Green Mark Platinum and efficient IT.
Google Dietzenbach data centre (Hesse)Germany
Hesse
AnnouncedbuildingEUR 5.5 billionInvestmentGoogle11 Nov 2025: Announced with heat recovery partnership
Google Elmina data centre (Selangor)Malaysia
Selangor
Under constructionbuildingUSD 2 billionInvestmentGoogle20 Aug 2026: Operations expected within about nine months
Google Grange Castle data centre extension (phase 3, Dublin)Ireland
South Dublin
Permittedphase72,400 sq mPermittedGoogle28 Sept 2026: An Coimisiún Pleanála granted permission for a 72,400 sq m extension at Google's Grange Castle campus after the council refused it in 2024, with conditions on PPAs and renewable backup fuel.
Google Waltham Cross data centre (Hertfordshire)United Kingdom
Hertfordshire, England
OperatingbuildingGBP 5 billionInvestmentGoogle16 Sept 2025: Data centre opened
Keppel Data Centres DC-CFA2 data centre (Jurong Island, Singapore)Singapore
Jurong Island
Provisional capacity allocationproject50 MWProvisional allocationKeppel Data Centres21 Aug 2026: EDB and IMDA provisionally allocated 50 MW each to Digital Realty, Equinix, Keppel Data Centres and STT GDC under the second Data Centre Call for Application. Winners committed to at least 50% green energy pathways, liquid cooling, Green Mark Platinum and efficient IT.
Meta Richland Parish data center (Hyperion, Louisiana)United States
Louisiana
Under constructioncampusat least USD 50 billionInvestmentMeta Platforms13 Jul 2026: Meta said its Louisiana site, home of the Hyperion cluster, will grow to 5 GW of compute capacity with more than $50 billion invested, naming DPR, Turner and Mortenson as general contractors.
Microsoft Fairwater 1 (Mount Pleasant, Wisconsin)
Part of Microsoft Mount Pleasant campus (Fairwater, Wisconsin)
United States
Wisconsin
Operatingphase1,200,000 sq ftOperatingMicrosoft23 Jun 2026: Microsoft said the first Mount Pleasant facility was fully operational on 23 June 2026, with a second facility due in 2028. The site uses closed-loop liquid cooling for over 90% of capacity.
Microsoft Mount Pleasant campus (Fairwater, Wisconsin)United States
Wisconsin
Under constructioncampusUSD 4.7 billionInvestmentMicrosoft23 Jun 2026: Microsoft said the first Mount Pleasant facility was fully operational on 23 June 2026, with a second facility due in 2028. The site uses closed-loop liquid cooling for over 90% of capacity.
Microsoft Rhenish mining area data centre cluster (Bergheim, Bedburg, Elsdorf)Germany
North Rhine-Westphalia
Under constructioncampusEUR 3.2 billionInvestmentMicrosoft12 Mar 2026: Groundbreaking in Bergheim, permits for Bergheim and Bedburg
Microsoft second Mount Pleasant facility (Wisconsin)
Part of Microsoft Mount Pleasant campus (Fairwater, Wisconsin)
United States
Wisconsin
Under constructionphasenot disclosedMicrosoft23 Jun 2026: Microsoft said the first Mount Pleasant facility was fully operational on 23 June 2026, with a second facility due in 2028. The site uses closed-loop liquid cooling for over 90% of capacity.
Nscale Loughton AI data centre (Essex)United Kingdom
Essex, England
Delayedprojectup to 90 MWAnnouncedNscale18 Oct 2026: Reuters and the Guardian, citing the Telegraph, reported on 18 October 2026 that Microsoft ended its agreement for Nscale's planned AI data centre at Loughton, Essex. A month earlier the Guardian reported UK Power Networks might not supply enough power until the early to mid 2030s, against a 2027 target. Nscale says it is pursuing alternative power.
QTS Cambois campus phase 1 (two data halls)
Part of QTS Cambois data centre campus (Blyth, Northumberland)
United Kingdom
Northumberland, England
Permittedphasenot disclosedQTS Data Centers, Blackstone2 Dec 2025: Phase 1 reserved matters (two data halls) approved
QTS Cambois data centre campus (Blyth, Northumberland)United Kingdom
Northumberland, England
Under constructioncampusGBP 10 billionInvestmentQTS Data Centers, Blackstone2 Dec 2025: Phase 1 reserved matters (two data halls) approved
ST Telemedia Global Data Centres DC-CFA2 data centre (Jurong Island, Singapore)Singapore
Jurong Island
Provisional capacity allocationproject50 MWProvisional allocationST Telemedia Global Data Centres21 Aug 2026: EDB and IMDA provisionally allocated 50 MW each to Digital Realty, Equinix, Keppel Data Centres and STT GDC under the second Data Centre Call for Application. Winners committed to at least 50% green energy pathways, liquid cooling, Green Mark Platinum and efficient IT.
Stargate UAE AI infrastructure cluster (1 GW)
Part of UAE-US AI Campus (Abu Dhabi)
United Arab Emirates
Abu Dhabi
Under constructioncampusUSD 30 billionInvestmentKhazna Data Centers11 Sept 2026: Reuters reported, citing anonymous sources, that the UAE is revising its single-site Abu Dhabi AI campus after the Iran conflict, toward a network of protected and partly underground sites. Stargate UAE's first 200 MW was still described as due in 2026.
Stargate UAE first 200 MW
Part of Stargate UAE AI infrastructure cluster (1 GW)
United Arab Emirates
Abu Dhabi
Under constructionphasenot disclosedKhazna Data Centers11 Sept 2026: Reuters reported, citing anonymous sources, that the UAE is revising its single-site Abu Dhabi AI campus after the Iran conflict, toward a network of protected and partly underground sites. Stargate UAE's first 200 MW was still described as due in 2026.
UAE-US AI Campus (Abu Dhabi)United Arab Emirates
Abu Dhabi
Under constructioncampusnot disclosedG4211 Sept 2026: Reuters reported, citing anonymous sources, that the UAE is revising its single-site Abu Dhabi AI campus after the Iran conflict, toward a network of protected and partly underground sites. Stargate UAE's first 200 MW was still described as due in 2026.
Vantage DUB11 Profile Park campus (Clondalkin, Dublin)Ireland
South Dublin
Delayedcampus52 MWUnder constructionVantage Data Centers24 Jul 2026: Filings show €151.7m impairment for delayed delivery

Capacity in tracked public coverage

Tracked public coverage, not a national total. Sums of reported, project-level figures from 9 of the 27 published project records we track for all published project records. Each metric and each delivery class is summed on its own and never added to another. Confirmed operating capacity never includes design or ultimate capacity. Delayed projects are never counted as under construction now. Campus and phase figures are not double counted. Ranges and upper bounds are not summed. Unknown values are not counted as zero.

MetricDelivery classSum of tracked recordsContributing records
InvestmentReported project investment
Project-level investment in one currency. Components of a total are not added again. Company-wide programmes are excluded.
USD 92 million
IT powerProvisional capacity allocation
Capacity provisionally allocated by an authority. This is not planning permission and not built capacity.
200 MW
IT powerAnnounced or design capacity (not delivered)
Ultimate, design or announced capacity. Not delivered capacity. Never added to confirmed figures.
at least 420 MW
Includes a lower-bound figure, so the sum is a minimum.
IT powerDelayed or on hold (current stage)
Projects currently delayed or on hold, with the capacity they were reported to deliver.
52 MW
Total facility powerAnnounced or design capacity (not delivered)
Ultimate, design or announced capacity. Not delivered capacity. Never added to confirmed figures.
1,200 MW
Figures not counted (27) and why

Method: capacity rules. Company-wide investment, area figures and third-party market estimates are never included in these sums.