Data centre developer in Ireland. RTÉ reported in March 2026 that Echelon is building DUB20 at Arklow in County Wicklow, due in 2028, as part of a EUR 4.2 billion investment in DUB20 and DUB30, with a 220 kV substation developed with SSE and access to offshore wind.
Footprint covered here
Project records on this site: Echelon DUB20 data centre (Arklow, Co Wicklow), under construction, no MW published.
Tracked projects
| Project | Role | Country | Stage |
|---|---|---|---|
| Echelon DUB20 data centre (Arklow, Co Wicklow) | Developer, Owner | Ireland | Under construction |
Markets
Sources (1), last checked 19 Oct 2026
- Echelon plans first Green Energy Park in Co Wicklow (opens in a new tab), RTÉ, published 26 Mar 2026, accessed 19 Oct 2026