Lambda AI factory (Kansas City, Missouri)
Lambda announced in October 2025 plans for an AI factory in Kansas City that it will develop and run as sole tenant, with more than 10,000 NVIDIA GPUs for a single customer. The site is expected to launch in early 2026 with 24 MW, with potential for more than 100 MW later. Lambda says the GPUs at launch will be NVIDIA Blackwell Ultra.
Reported figures
| Figure | What it measures | Delivery state | Scope and date | Used in totals | Source |
|---|---|---|---|---|---|
| 24 MW Official source | Otherbasis unclear Launch capacity. MW basis not stated Source wording: "launch in early 2026 with 24MW of capacity" | Planned Stage stated in source: Planned | campus 28 Oct 2025 | No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed. | lambda.ai (opens in a new tab) |
| at least 100 MW Official source Lower bound | Otherbasis unclear Potential later capacity, lower bound Source wording: "potential to scale up to more than 100MW" | Planned Stage stated in source: Target | campus 28 Oct 2025 | No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed. | lambda.ai (opens in a new tab) |
Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.
Sources (1), last checked 19 Oct 2026