Project record, campus

Lambda AI factory (Kansas City, Missouri)

Under constructionUnited StatesMissouri

Lambda announced in October 2025 plans for an AI factory in Kansas City that it will develop and run as sole tenant, with more than 10,000 NVIDIA GPUs for a single customer. The site is expected to launch in early 2026 with 24 MW, with potential for more than 100 MW later. Lambda says the GPUs at launch will be NVIDIA Blackwell Ultra.

Reported figures

Reported figures for Lambda AI factory (Kansas City, Missouri)
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
24 MW
Official source
Otherbasis unclear
Launch capacity. MW basis not stated
Source wording: "launch in early 2026 with 24MW of capacity"
Planned
Stage stated in source: Planned
campus
28 Oct 2025
No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed.lambda.ai (opens in a new tab)
at least 100 MW
Official source
Lower bound
Otherbasis unclear
Potential later capacity, lower bound
Source wording: "potential to scale up to more than 100MW"
Planned
Stage stated in source: Target
campus
28 Oct 2025
No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed.lambda.ai (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

Sources (1), last checked 19 Oct 2026
  1. Lambda Doubles Down on Midwest Expansion, To Build AI Factory in Kansas City, MO (opens in a new tab), Lambda, published 28 Oct 2025, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.