Equinix announced in November 2025 a USD 22 million data centre in Lagos, LG3, its first newly built site in West Africa and the first phase of about USD 100 million of planned investment in Africa over two years. It was set to open in Q1 2026. Opening was not rechecked for this record. Equinix said LG3 also brings Equinix Fabric to the Lagos metro.

Reported figures

Reported figures for Equinix LG3 (Lagos)
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
USD 22 million
Official source
22,000,000 USD
Investment
USD millions
Source wording: "The $22 Million investment in LG3"
Announced
Stage stated in source: Announced
campus
10 Nov 2025
No. Marked not summable by research: USD millionsnewsroom.equinix.com (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

Sources (1), last checked 19 Oct 2026
  1. Equinix announces plans for new $22 million data center in Lagos, Nigeria (opens in a new tab), Equinix, published 10 Nov 2025, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.