France

In France RTE signed an accelerated connection contract in January 2026 for the Campus IA site at Fouju, with 240 MW by the end of 2027 and 700 MW before the end of 2029. Some announced projects have also been withdrawn, such as Fluidstack in March 2026.

Tracked project records
4
Policy records
0
Cloud regions
0
Last checked
19 Oct 2026

Projects in France Policy timeline

Overview

At Cambrai, Data4 and Brookfield are developing the e-Valley campus on a former air base, described in 2025 as at least 300 MW in the short term with an ambition of 1 GW. South of Paris, Mistral AI raised USD 830 million of debt for a 44 MW GPU cluster at an Eclairion site in Bruyères-le-Châtel, though sources differ on whether it is running.

Grid context

RTE offers fast-track connections for large data centre sites. National data centre demand figures in the RTE outlook could not be verified as text for this release.

Latest changes

  1. Project 19 Oct 2026 Data4 and Brookfield e-Valley AI campus (Cambrai, former Air Base 103)Second land approval reported Third-party reported Related: Data4 and Brookfield e-Valley AI campus (Cambrai, former Air Base 103). dcmag.fr (opens in a new tab)
  2. Project 20 Mar 2026 Fluidstack AI data centre at Bosquel Business Park (withdrawn)Fluidstack reported to withdraw from French projects Third-party reported Related: Fluidstack AI data centre at Bosquel Business Park (withdrawn). datacenterdynamics.com (opens in a new tab)

All changes

Tracked projects

ProjectLevelStageOperator or developerLatest change
Campus IA (Fouju, Seine-et-Marne)campusPlanningCampus IAnot disclosed
Data4 and Brookfield e-Valley AI campus (Cambrai, former Air Base 103)campusPlanningData4, Brookfield19 Oct 2026: Second land approval reported
Fluidstack AI data centre at Bosquel Business Park (withdrawn)campusCancelled20 Mar 2026: Fluidstack reported to withdraw from French projects
Mistral AI compute cluster at Eclairion (Bruyères-le-Châtel, Essonne)campusUnder constructionEclairionnot disclosed

Filter all projects by France

Capacity in tracked public coverage

Tracked public coverage, not a national total. Sums of reported, project-level figures from 0 of the 4 published project records we track for France. Each metric and each delivery class is summed on its own and never added to another. Confirmed operating capacity never includes design or ultimate capacity. Delayed projects are never counted as under construction now. Campus and phase figures are not double counted. Ranges and upper bounds are not summed. Unknown values are not counted as zero.

None of the tracked project records for France has a figure that can be summed yet. Figures with an unclear basis and undisclosed values are never added. Each project page lists its reported figures as published. Not disclosed is not zero.

Figures not counted (6) and why

Method: capacity rules. Company-wide investment, area figures and third-party market estimates are never included in these sums.

Hyperscaler and AI cloud activity in France

4 tracked projects in France, of which 2 involve a hyperscaler or AI cloud as owner, operator, developer or a stated or reported tenant. Part of the Europe, Middle East and Africa (EMEA) region on the hyperscaler and cloud hub.

Hyperscaler and AI cloud projects in France
ProjectStageOperator, developer or ownerHyperscaler or AI tenantAnnouncedExpected
Fluidstack AI data centre at Bosquel Business Park (withdrawn)
Somme (Hauts-de-France)
Cancellednot disclosedFluidstack (reported)not statednot stated
Mistral AI compute cluster at Eclairion (Bruyères-le-Châtel, Essonne)
Île-de-France
Under construction
Disputed
EclairionMistral AI (reported)not stated2026-06

Capacity, forecasts and market share: France

Every number is shown as published, with its basis, date and source. Figures with different bases (IT power, grid connection, electricity use) or from different sources are never added or blended. Where no figure exists we say not publicly reported. CoolPower makes no forecasts of its own.

Current capacity and pipeline

Current capacity and pipeline, France
FigureWhat it measuresStatePeriod or as ofSource
240 MW
Official source
Grid connection
First power step in the RTE accelerated connection contract for the Campus IA site at Fouju (single project, not national capacity)
Source statement (paraphrased): "un premier palier de puissance de 240 MW d’ici fin 2027"
Contracted or grantedby end 2027RTE (opens in a new tab)
Published 22 Jan 2026. Accessed 19 Oct 2026.
700 MW
Official source
Grid connection
Second power step for the same Campus IA connection (700 MW is the second step as stated, not added to the 240 MW here)
Source statement (paraphrased): "un second palier de 700 MW avant fin 2029"
Contracted or grantedbefore end 2029RTE (opens in a new tab)
Published 22 Jan 2026. Accessed 19 Oct 2026.

Forecasts and scenarios

Forecast: not publicly reported by a named publisher in a source we could check.

RTE, Contracted or granted, by end 2027: 240 MW. RTE, Contracted or granted, before end 2029: 700 MW. Bars are separate published figures and are not added together.RTE: Grid connection, contracted or granted, by end 2027240 MWRTE: Grid connection, contracted or granted, before end 2029700 MW
MW. Solid bars: current. Lighter bars: pipeline. Dashed outline bars: forecasts or scenarios. A range is drawn from its low to its high end. The data table is above.

Cloud market share

Provider market share: not publicly reported. No public provider market share by country was found except mainland China (Omdia via DCD). Every other country page shows not publicly reported.

Download these 2 figures as CSV All market figures (CSV)

Cloud regions in France

A cloud region is a provider's service area. It is not a data centre campus and has no MW figure here.

No cloud regions recorded.

Policy timeline

No policy records published.

Operators and developers

Sources (4), last checked 19 Oct 2026
  1. Campus IA et RTE: contrat de raccordement accéléré (press release) (opens in a new tab), RTE, published 22 Jan 2026, accessed 19 Oct 2026
  2. Fluidstack drops data center projects in France to focus on US (report) (opens in a new tab), DatacenterDynamics, published 20 Mar 2026, accessed 19 Oct 2026
  3. Cambrai : le méga data center e-Valley de Data4 et Brookfield reçoit un second feu vert foncier (opens in a new tab), DCmag, published 19 Oct 2026, accessed 19 Oct 2026
  4. Mistral AI raises $830m in debt financing for data center in Paris, France (opens in a new tab), DatacenterDynamics, published 30 Mar 2026, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.