Operator profile

Campus IA

Developer

Developer of the Campus IA AI data centre at Fouju in Seine-et-Marne, France. RTE signed an accelerated grid connection contract in January 2026 for a first step of 240 MW by the end of 2027 and 700 MW before the end of 2029.

Footprint covered here

Project records on this site: Campus IA (Fouju, Seine-et-Marne), in planning, 240 MW as stated.

Tracked projects

ProjectRoleCountryStage
Campus IA (Fouju, Seine-et-Marne)DeveloperFrancePlanning

Markets

Sources (1), last checked 19 Oct 2026
  1. Campus IA et RTE: contrat de raccordement accéléré (press release) (opens in a new tab), RTE, published 22 Jan 2026, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.