UKAEA invited expressions of interest in August 2025 from partners to build a mission-led AI data centre at its Culham campus, part of the first UK AI Growth Zone. The invitation describes about 100 MW initially with the potential to grow towards 500 MW. No partner was named in the source checked. UKAEA would first release at least 10 acres of land and its reconfigured power connections.

Reported figures

Reported figures for Culham AI Growth Zone data centre (Oxfordshire)
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
about 100 MW
Official source
Approximate
Otherbasis unclear
Initial power, steady state and dual resilient as described. Not stated as IT load
Source wording: "approximately 100MW of steady state, dual resilient power"
Planned
Stage stated in source: Planned
campus
12 Aug 2025
No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed.culham.org.uk (opens in a new tab)
up to 500 MW
Official source
Upper bound
Otherbasis unclear
Possible later scale, upper bound
Source wording: "potentially up to a maximum limit of 500MW"
Planned
Stage stated in source: Target
campus
12 Aug 2025
No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed.culham.org.uk (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

Sources (1), last checked 19 Oct 2026
  1. Invitation to Express Interest: mission-led AI data centre at Culham (opens in a new tab), UKAEA Culham Campus, published 12 Aug 2025, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.