Operator profile

ODATA

Colocation ownerColocation operator

Latin American data centre operator and part of Aligned Data Centers. In February 2026 it switched on the first building of its QR03 campus at El Marqués, Querétaro, with 72 MW of IT power for hyperscale cloud and AI customers, according to DCD. The campus is planned for up to 300 MW of IT in five buildings on almost 275,000 square metres, with more than USD 3 billion of investment.

Footprint covered here

Project records on this site: ODATA QR03 (Querétaro), operating, 72 MW as stated.

Tracked projects

ProjectRoleCountryStage
ODATA QR03 (Querétaro)Operator, OwnerMexicoOperating

Markets

Sources (1), last checked 19 Oct 2026
  1. ODATA enciende QR03 y consolida el mayor campus de data centers de México para la era de la IA (opens in a new tab), DatacenterDynamics en español, published 23 Feb 2026, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.