Project record, campus

Schwarz Digits AI data centre (Lübbenau, Brandenburg)

Under constructionGermanyBrandenburg

Schwarz Digits, the IT arm of the Schwarz Group, is building an AI data centre on a 13 hectare former power plant site in Lübbenau. The company names an investment of EUR 11 billion, two construction phases, room for up to 100,000 GPUs and completion by the end of 2027. Waste heat is planned to feed district heating from 2028 for up to 75,000 households.

Reported figures

Reported figures for Schwarz Digits AI data centre (Lübbenau, Brandenburg)
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
about 200 MW
Official source
Approximate
Grid connection
Grid connection capacity as stated by the company
Source wording: "Anschlussleistung von rund 200 Megawatt"
Planned
Stage stated in source: Planned
campus
date not given, seen 19 Oct 2026
No. Marked not summable by research: Grid connection capacity as stated by the companyschwarz-digits.de (opens in a new tab)
EUR 11 billion
Official source
11,000,000,000 EUR
Investment
Investment in EUR billions
Source wording: "Investition von elf Milliarden Euro"
Announced
Stage stated in source: Announced
campus
date not given, seen 19 Oct 2026
No. Marked not summable by research: Investment in EUR billionsschwarz-digits.de (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

Cooling

Waste heat to be used for district heating from 2028, up to 75,000 households according to the company. schwarz-digits.de (opens in a new tab)

Power and grid

About 200 MW grid connection (Anschlussleistung) stated by the company. schwarz-digits.de (opens in a new tab)

Sources (1), last checked 19 Oct 2026
  1. Datacenter Lübbenau: Schwarz Digits investiert in digitale Souveränität (opens in a new tab), Schwarz Digits, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.