Project record, campus
Google Middenmeer data centre
Google data centre at Middenmeer in North Holland. Google states an investment of EUR 500 million to date at the site and describes a mix of traditional and renewable energy infrastructure nearby. Capacity in MW and the date of the investment figure are not published on the page. Google expected Middenmeer to receive 80% of its energy from renewable sources such as wind and solar in 2024.
Reported figures
| Figure | What it measures | Delivery state | Scope and date | Used in totals | Source |
|---|---|---|---|---|---|
| EUR 500 million Official source 500,000,000 EUR | Investment Cumulative investment in EUR millions, date not stated Source wording: "data centre investment of EUR 500 million to date" | Design or ultimate capacity The source gives the whole-campus figure. The share that is operating is not disclosed, so it is treated as design capacity. Stage stated in source: Operating | campus 2026 | No. Marked not summable by research: Cumulative investment in EUR millions, date not stated | datacenters.google (opens in a new tab) |
Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.
Sources (1), last checked 19 Oct 2026
- Middenmeer, Netherlands data center location page (opens in a new tab), Google Data Centers, accessed 19 Oct 2026
Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.