Operator profile

EcoDataCenter

Colocation ownerDeveloper

Data centre company founded in Sweden, with sites including EcoDataCenter 1 in Falun. It is building EcoDataCenter 2 on the former Kvarnsveden paper mill site in Borlänge with access to 250 MW at launch and potential for 600 MW, and named Mistral AI as a user of the campus in February 2026.

Footprint covered here

Project records on this site: EcoDataCenter 2 campus (Kvarnsveden, Borlänge), under construction, 250 MW as stated.

Tracked projects

ProjectRoleCountryStage
EcoDataCenter 2 campus (Kvarnsveden, Borlänge)Developer, OwnerSwedenUnder construction

Markets

Sources (2), last checked 19 Oct 2026
  1. EcoDataCenter breaks ground on mega campus in Borlänge (opens in a new tab), EcoDataCenter, accessed 19 Oct 2026
  2. EcoDataCenter och Mistral AI bygger storskalig europeisk AI-infrastruktur i Borlänge (opens in a new tab), EcoDataCenter, published 11 Feb 2026, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.