Project record, campus

Microsoft Rhenish mining area data centre cluster (Bergheim, Bedburg, Elsdorf)

Under constructionGermanyNorth Rhine-Westphalia

Cluster of three Microsoft hyperscale data centres in the Rhenish lignite region of North Rhine-Westphalia. Ground was broken in Bergheim on 12 March 2026, with building permits granted for Bergheim and Bedburg and Elsdorf to follow. Microsoft says the sites will use a closed-loop cooling concept without evaporative water loss. WDR reports the first data centre is due for completion in 2028 and cites Microsoft's €3.2 billion German AI and cloud investment, which is a company-level figure. Capacity not disclosed.

Reported figures

Reported figures for Microsoft Rhenish mining area data centre cluster (Bergheim, Bedburg, Elsdorf)
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
EUR 3.2 billion
Disputed
3,200,000,000 EUR
Investment
Microsoft Germany AI and cloud infrastructure investment, EUR billions. Scope across Germany per Microsoft 2024 announcement, attributed to the region by WDR. Not a verified project budget.
Source wording: "3,2 Milliarden Euro will Microsoft in der Region investieren"
Announced
Stage stated in source: Announced
company
12 Mar 2026
No. Scope is company, not one physical project. Not attributable to this asset.www1.wdr.de (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

Cooling

Closed-loop cooling with no evaporative water use, refilled almost never after initial fill (Microsoft). news.microsoft.com (opens in a new tab)

What changed

  1. 12 Mar 2026 Groundbreaking in Bergheim, permits for Bergheim and Bedburg Related: Microsoft. news.microsoft.com (opens in a new tab)

Technologies

Relevant policy

Sources (2), last checked 18 Oct 2026
  1. Spatenstich für Rechenzentrums-Cluster in Nordrhein-Westfalen (opens in a new tab), Microsoft Source EMEA, published 12 Mar 2026, accessed 18 Oct 2026
  2. Spatenstich für Microsoft-Rechenzentren in Bergheim (opens in a new tab), WDR, published 12 Mar 2026, accessed 18 Oct 2026

Last checked 18 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.