Project record, campus

Nebius second Mäntsälä data centre

Under constructionFinlandUusimaa

Nebius announced in August 2026 a second data centre at Mäntsälä with up to 70 MW coming online from 2027. Caverion said in October 2026 it will deliver a EUR 15 million 70 MW substation for the site, to be completed in autumn 2027. Caverion says the new 70 MW building sits beside the existing 75 MW site, and that delivery of the substation alone will employ about 80 energy sector professionals and electricians.

Reported figures

Reported figures for Nebius second Mäntsälä data centre
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
up to 70 MW
Third-party reported
Upper bound
Otherbasis unclear
Site capacity, upper bound. MW basis not stated
Source wording: "capacity of up to 70MW coming online from 2027"
Planned
Stage stated in source: Planned
campus
13 Aug 2026
No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed.datacenterdynamics.com (opens in a new tab)
70 MW
Official source
Grid connection
Substation rating
Source wording: "The substation will have a capacity of 70 megawatts"
Planned
Stage stated in source: Under construction
campus
2 Oct 2026
No. Marked not summable by research: Substation ratingcaverion.com (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

Power and grid

70 MW substation by Caverion, due autumn 2027. caverion.com (opens in a new tab)

Sources (2), last checked 19 Oct 2026
  1. Nebius expands European presence, announces deployment in Estonia and second data center in Mäntsälä, Finland (opens in a new tab), DatacenterDynamics, published 13 Aug 2026, accessed 19 Oct 2026
  2. Caverion Finland will deliver a EUR 15 million substation for AI cloud company Nebius (opens in a new tab), Caverion, published 2 Oct 2026, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.