In Finland Fingrid reported in August 2026 nearly 5 GW of planned final capacity from data centre projects with signed connection agreements. Google Hamina and the Microsoft sites at Espoo and Kirkkonummi feed waste heat into district heating networks.

Tracked project records
6
Policy records
0
Cloud regions
0
Last checked
19 Oct 2026

Projects in Finland Policy timeline

Overview

Google plans at least EUR 13 billion for 2027 and 2028 across Hamina, Kajaani, Muhos and Vaala, but preparatory work at Kajaani and Muhos was ordered to stop in October 2026 pending environmental impact assessments. Nebius is tripling its Mäntsälä site to 75 MW and building a second Mäntsälä data centre of up to 70 MW from 2027. Yle reported about 50,000 MW of connection enquiries, of which Fingrid expects about a tenth to be built.

Grid context

Yle reported in April 2026 more than 50,000 MW of data centre connection enquiries, of which Fingrid expects about one tenth to be realised.

Latest changes

  1. Project 6 Oct 2026 Google Kajaani data centre (Kainuu)Agency orders halt to preparatory work pending environmental assessment Related: Google Kajaani data centre (Kainuu), Google Muhos data centre (North Ostrobothnia). bbc.com (opens in a new tab)
  2. Project 18 May 2026 Google Hamina data centre campusHeat recovery plant supplying district heating since Q4 2025 Related: Google Hamina data centre campus. capman.com (opens in a new tab)
  3. Project 6 May 2026 Microsoft data centres at Hepokorpi (Espoo) and Kolabacken (Kirkkonummi)Fortum heat plants at both sites start operating Related: Microsoft data centres at Hepokorpi (Espoo) and Kolabacken (Kirkkonummi). fortum.com (opens in a new tab)

All changes

Tracked projects

ProjectLevelStageOperator or developerLatest change
Google Hamina data centre campuscampusOperatingGoogle18 May 2026: Heat recovery plant supplying district heating since Q4 2025
Google Kajaani data centre (Kainuu)campusOn holdGoogle6 Oct 2026: Agency orders halt to preparatory work pending environmental assessment
Google Muhos data centre (North Ostrobothnia)campusOn holdGoogle6 Oct 2026: Agency orders halt to preparatory work pending environmental assessment
Microsoft data centres at Hepokorpi (Espoo) and Kolabacken (Kirkkonummi)campusNot disclosedMicrosoft6 May 2026: Fortum heat plants at both sites start operating
Nebius Mäntsälä data centre (first site)campusOperatingNebiusnot disclosed
Nebius second Mäntsälä data centrecampusUnder constructionNebiusnot disclosed

Filter all projects by Finland

Capacity in tracked public coverage

Tracked public coverage, not a national total. Sums of reported, project-level figures from 0 of the 6 published project records we track for Finland. Each metric and each delivery class is summed on its own and never added to another. Confirmed operating capacity never includes design or ultimate capacity. Delayed projects are never counted as under construction now. Campus and phase figures are not double counted. Ranges and upper bounds are not summed. Unknown values are not counted as zero.

None of the tracked project records for Finland has a figure that can be summed yet. Figures with an unclear basis and undisclosed values are never added. Each project page lists its reported figures as published. Not disclosed is not zero.

Figures not counted (4) and why

Method: capacity rules. Company-wide investment, area figures and third-party market estimates are never included in these sums.

Hyperscaler and AI cloud activity in Finland

6 tracked projects in Finland, of which 6 involve a hyperscaler or AI cloud as owner, operator, developer or a stated or reported tenant. Part of the Europe, Middle East and Africa (EMEA) region on the hyperscaler and cloud hub.

Hyperscaler and AI cloud projects in Finland
ProjectStageOperator, developer or ownerHyperscaler or AI tenantAnnouncedExpected
Google Hamina data centre campus
Kymenlaakso
OperatingGooglenot stated2024-05-20not stated
Google Kajaani data centre (Kainuu)
Kainuu
On holdGooglenot stated2026-09-09not stated
Google Muhos data centre (North Ostrobothnia)
North Ostrobothnia
On holdGooglenot stated2026-09-09not stated
Microsoft data centres at Hepokorpi (Espoo) and Kolabacken (Kirkkonummi)
Uusimaa
Not disclosedMicrosoftnot statednot statednot stated
Nebius Mäntsälä data centre (first site)
Uusimaa
OperatingNebiusnot stated2024-10-08not stated
Nebius second Mäntsälä data centre
Uusimaa
Under constructionNebiusnot stated2026-08-132027

Capacity, forecasts and market share: Finland

Every number is shown as published, with its basis, date and source. Figures with different bases (IT power, grid connection, electricity use) or from different sources are never added or blended. Where no figure exists we say not publicly reported. CoolPower makes no forecasts of its own.

Current capacity and pipeline

Current capacity and pipeline, Finland
FigureWhat it measuresStatePeriod or as ofSource
about 5 GW
Official source
Grid connection
Planned final capacity of data centre projects with signed connection agreements, based on developer information and including distribution grid connections
Source statement (paraphrased): "nearly 5 GW of planned final capacity with signed connection agreements"
Contracted or granted2026-08-18Fingrid (opens in a new tab)
Published 18 Aug 2026. Accessed 19 Oct 2026.
more than 50,000 MW
Third-party reported
Grid requests
Data centre connection enquiries reported by Yle. Fingrid expects about 10% (around 5,000 MW) to be realised
Source statement (paraphrased): "over 50,000 MW of enquiries"
Requested2026-04-10Yle (opens in a new tab)
Published 10 Apr 2026. Accessed 19 Oct 2026.

Sources measure different things (for example colocation only, grid requests or contracted connections), so they are listed side by side.

Forecasts and scenarios

Forecast: not publicly reported by a named publisher in a source we could check.

Fingrid, Contracted or granted, 2026-08-18: about 5 GW. Bars are separate published figures and are not added together.Fingrid: Grid connection, contracted or granted, 2026-08-18about 5 GW
GW. Solid bars: current. Lighter bars: pipeline. Dashed outline bars: forecasts or scenarios. A range is drawn from its low to its high end. The data table is above.
Yle, Requested, 2026-04-10: more than 50,000 MW. Bars are separate published figures and are not added together.Yle: Grid requests, requested, 2026-04-10more than 50,000 MW
MW. Solid bars: current. Lighter bars: pipeline. Dashed outline bars: forecasts or scenarios. A range is drawn from its low to its high end. The data table is above.

Cloud market share

Provider market share: not publicly reported. No public provider market share by country was found except mainland China (Omdia via DCD). Every other country page shows not publicly reported.

Download these 2 figures as CSV All market figures (CSV)

Cloud regions in Finland

A cloud region is a provider's service area. It is not a data centre campus and has no MW figure here.

No cloud regions recorded.

Policy timeline

No policy records published.

Operators and developers

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.