In Belgium Google runs a data centre campus at Saint-Ghislain in Wallonia and in October 2025 announced EUR 5 billion for 2026 and 2027 to expand it. Its second campus at Farciennes lost a Sambre water permit in August 2026. Microsoft opened its Belgium Central cloud region in November 2025. No national capacity figure or Elia data centre forecast could be checked.

Tracked project records
3
Policy records
0
Cloud regions
0
Last checked
19 Oct 2026

Projects in Belgium Policy timeline

Grid context

Elia, the transmission operator, publishes demand scenarios, but the data centre figures in its 2025 working group slides could not be retrieved and checked, so none are shown.

Latest changes

  1. Project 16 Aug 2026 Google Farciennes data centre campus (Hainaut)Sambre water pumping permit refused Related: Google Farciennes data centre campus (Hainaut). 21news.be (opens in a new tab)
  2. Project 18 Nov 2025 Microsoft Belgium Central cloud region data centresBelgium Central region opened Related: Microsoft Belgium Central cloud region data centres. pulse.microsoft.com (opens in a new tab)

All changes

Tracked projects

ProjectLevelStageOperator or developerLatest change
Google Farciennes data centre campus (Hainaut)campusDelayed16 Aug 2026: Sambre water pumping permit refused
Google Saint-Ghislain data centre campuscampusOperatingGooglenot disclosed
Microsoft Belgium Central cloud region data centrescampusOperatingMicrosoft18 Nov 2025: Belgium Central region opened

Filter all projects by Belgium

Capacity in tracked public coverage

Tracked public coverage, not a national total. Sums of reported, project-level figures from 0 of the 3 published project records we track for Belgium. Each metric and each delivery class is summed on its own and never added to another. Confirmed operating capacity never includes design or ultimate capacity. Delayed projects are never counted as under construction now. Campus and phase figures are not double counted. Ranges and upper bounds are not summed. Unknown values are not counted as zero.

None of the tracked project records for Belgium has a figure that can be summed yet. Figures with an unclear basis and undisclosed values are never added. Each project page lists its reported figures as published. Not disclosed is not zero.

Figures not counted (2) and why

Method: capacity rules. Company-wide investment, area figures and third-party market estimates are never included in these sums.

Hyperscaler and AI cloud activity in Belgium

3 tracked projects in Belgium, of which 3 involve a hyperscaler or AI cloud as owner, operator, developer or a stated or reported tenant. Part of the Europe, Middle East and Africa (EMEA) region on the hyperscaler and cloud hub.

Hyperscaler and AI cloud projects in Belgium
ProjectStageOperator, developer or ownerHyperscaler or AI tenantAnnouncedExpected
Google Farciennes data centre campus (Hainaut)
Hainaut (Wallonia)
DelayedGooglenot stated2024-04-08not stated
Google Saint-Ghislain data centre campus
Hainaut (Wallonia)
OperatingGooglenot stated2025-10-08not stated
Microsoft Belgium Central cloud region data centresOperatingMicrosoftnot stated2025-11-18not stated

Capacity, forecasts and market share: Belgium

Every number is shown as published, with its basis, date and source. Figures with different bases (IT power, grid connection, electricity use) or from different sources are never added or blended. Where no figure exists we say not publicly reported. CoolPower makes no forecasts of its own.

Current capacity and pipeline

Operational, under construction and planned capacity: not publicly reported in a source we could check.

Forecasts and scenarios

Forecast: not publicly reported by a named publisher in a source we could check.

Cloud market share

Provider market share: not publicly reported. No public provider market share by country was found except mainland China (Omdia via DCD). Every other country page shows not publicly reported.

No figures to download yet. All market figures (CSV)

Cloud regions in Belgium

A cloud region is a provider's service area. It is not a data centre campus and has no MW figure here.

No cloud regions recorded.

Policy timeline

No policy records published.

Operators and developers

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.