Project record, campus

OADC LOS1 (Lagos)

Under constructionNigeriaLagos

Open Access Data Centres lists a 24 MW data centre in Lagos. Techeconomy reported in July 2026 an initial 6 MW phase scalable to 24 MW and that OADC is looking at gas for power. OADC lists 7,200 square metres of technical space and N+1 cooling redundancy for the site, aimed at high-density colocation and hyperscale requirements.

Reported figures

Reported figures for OADC LOS1 (Lagos)
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
24 MW
Official source
Otherbasis unclear
Full build. MW basis not stated
Source wording: "24MW"
Planned
Stage stated in source: Planned
campus
date not given, seen 19 Oct 2026
No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed.openaccessdc.net (opens in a new tab)
6 MW
Third-party reported
Otherbasis unclear
First phase as reported
Source wording: "an initial 6 MW phase"
Planned
Stage stated in source: Planned
campus
14 Jul 2026
No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed.techeconomy.ng (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

Power and grid

Gas supply being considered, as reported by Techeconomy. techeconomy.ng (opens in a new tab)

Sources (2), last checked 19 Oct 2026
  1. OADC Lagos (LOS1) (opens in a new tab), Open Access Data Centres, accessed 19 Oct 2026
  2. EXCLUSIVE: OADC Explores Option of Using Gas to Power Data Centre in Nigeria (opens in a new tab), Techeconomy, published 14 Jul 2026, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.