Project record, campus
Microsoft Sweden Central data centres (Gävle, Sandviken, Staffanstorp)
Microsoft announced in June 2024 a SEK 33.7 billion investment over two years in Swedish cloud and AI infrastructure, including about 20,000 GPUs in its existing data centre sites in Sandviken, Gävle and Staffanstorp. Capacity in MW is not published. Microsoft says it has invested in almost 1,000 MW of renewable generation in Sweden, more than 800 MW of it operating, and that the region runs on fossil-free energy with hourly matching.
Reported figures
| Figure | What it measures | Delivery state | Scope and date | Used in totals | Source |
|---|---|---|---|---|---|
| SEK 33.7 billion Official source 33,700,000,000 SEK | Investment SEK billions over two years, covers more than the data centres Source wording: "33,7 miljarder kronor" | Announced Stage stated in source: Announced | campus 3 Jun 2024 | No. Marked not summable by research: SEK billions over two years, covers more than the data centres | news.microsoft.com (opens in a new tab) |
Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.
Sources (1), last checked 19 Oct 2026
- Microsoft tillkännager en investering på 33,7 miljarder kronor under två år i moln- och AI-infrastruktur (opens in a new tab), Microsoft Sverige, published 3 Jun 2024, accessed 19 Oct 2026
Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.