DataVita and CoreWeave Lanarkshire AI Growth Zone (Airdrie)

AnnouncedUnited KingdomScotland

The UK government named Lanarkshire an AI Growth Zone in January 2026, centred on DataVita's site at Airdrie with CoreWeave. The government release gives more than 500 MW of on-site power generation planned within four years and more than 3,400 jobs, figures it attributes to DataVita. It cites GBP 8.2 billion of private investment and a community fund of up to GBP 543 million over 15 years.

Reported figures

Reported figures for DataVita and CoreWeave Lanarkshire AI Growth Zone (Airdrie)
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
at least 500 MW
Official source
Lower bound
Otherbasis unclear
On-site generation, lower bound. Not IT load
Source wording: "more than 500MW of on-site power"
Planned
Stage stated in source: Planned
campus
29 Jan 2026
No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed.gov.uk (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

Power and grid

More than 500 MW of on-site generation planned within four years, as supplied by DataVita. gov.uk (opens in a new tab)

Sources (1), last checked 19 Oct 2026
  1. Lanarkshire named latest AI Growth Zone (opens in a new tab), GOV.UK (Department for Science, Innovation and Technology), published 29 Jan 2026, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.