Campus of more than 1 GW planned by Related Digital in Saline Township, Michigan, exclusively for Oracle as part of the OpenAI and Oracle Stargate partnership for 4.5 GW of additional capacity. Construction was expected to begin in early 2026. The design uses a closed-loop cooling system. The campus is being developed on 250 acres.

Reported figures

Reported figures for Stargate campus, Saline Township (Michigan)
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
at least 1 GW
Official source
Lower bound
Otherbasis unclear
Campus capacity, basis not stated
Source wording: "more than a gigawatt of capacity"
Planned
Stage stated in source: Announced
campus
30 Oct 2025
No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed.related.com (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

Cooling

Closed-loop cooling system, LEED certified design. related.com (opens in a new tab)

Sources (1), last checked 19 Oct 2026
  1. OpenAI, Oracle and Related Digital announce Stargate data center site in Michigan (opens in a new tab), Related Companies, published 30 Oct 2025, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.