Abilene AI campus phase 1 (two buildings)
Initial phase of the Crusoe-built Abilene campus: two buildings totalling 980,000 sq ft and more than 200 MW, construction started June 2024 and energisation expected in the first half of 2025 (Crusoe, March 2025). Each building is designed for up to 50,000 NVIDIA GB200 NVL72 on a single network fabric. Operating status after energisation is not confirmed in a primary source reviewed here, so stage stays under construction.
Part of Abilene AI campus at Lancium Clean Campus (Stargate Abilene, Texas). Capacity roll-ups count the parent figure and do not add this record again.
Reported figures
| Figure | What it measures | Delivery state | Scope and date | Used in totals | Source |
|---|---|---|---|---|---|
| at least 200 MW Official source Lower bound | Total facility power Phase power capacity, lower bound ("200+"). Parent campus figure includes this phase, so not eligible for roll-up. Source wording: "two buildings at 980,000 square feet and 200+ megawatts" | Under construction Stage stated in source: Under construction | phase 18 Mar 2025 | No. Marked not summable by research: Phase power capacity, lower bound ("200+"). Parent campus figure includes this phase, so not eligible for roll-up. | crusoe.ai (opens in a new tab) |
Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.
What changed
- 18 Mar 2025 Abilene AI campus at Lancium Clean Campus (Stargate Abilene, Texas)Phase two construction started (six buildings) Related: Abilene AI campus at Lancium Clean Campus (Stargate Abilene, Texas). crusoe.ai (opens in a new tab)
Sources (1), last checked 18 Oct 2026
- Crusoe expands AI data center campus in Abilene to 1.2 gigawatts (opens in a new tab), Crusoe, published 18 Mar 2025, accessed 18 Oct 2026