Market profile

Norway

In Norway NVE reports that data centres used about 3 TWh in 2025 and forecasts about 8 TWh in 2030, with about 10 GW of data centre capacity reserved or queued in the Statnett transmission grid. Stargate Norway at Narvik is the largest announced project.

Tracked project records
2
Policy records
0
Cloud regions
0
Last checked
19 Oct 2026

Projects in Norway Policy timeline

Overview

Google began building its first Norwegian data centre at Skien in February 2024 with EUR 600 million and 240 MW allocated for the first phase, and plans to reuse the heat. Stargate Norway at Kvandal outside Narvik is planned by Nscale with Aker and OpenAI for 230 MW, with an ambition of 290 MW more.

Grid context

NVE describes about 10 GW of reserved and queued data centre capacity in the Statnett grid, far above current use.

Tracked projects

ProjectLevelStageOperator or developerLatest change
Google Skien data centre (Gromstul, Telemark)campusUnder constructionGooglenot disclosed
Stargate Norway (Kvandal, Narvik)campusAnnouncedNscale, Akernot disclosed

Filter all projects by Norway

Capacity in tracked public coverage

Tracked public coverage, not a national total. Sums of reported, project-level figures from 0 of the 2 published project records we track for Norway. Each metric and each delivery class is summed on its own and never added to another. Confirmed operating capacity never includes design or ultimate capacity. Delayed projects are never counted as under construction now. Campus and phase figures are not double counted. Ranges and upper bounds are not summed. Unknown values are not counted as zero.

None of the tracked project records for Norway has a figure that can be summed yet. Figures with an unclear basis and undisclosed values are never added. Each project page lists its reported figures as published. Not disclosed is not zero.

Figures not counted (4) and why
  • Google Skien data centre (Gromstul, Telemark)
    • Grid connection 240 MW: Marked not summable by research: Power allocated for phase one. Not IT load
    • Investment EUR 600 million: Marked not summable by research: Investment in EUR millions
  • Stargate Norway (Kvandal, Narvik)
    • Other 230 MW: Basis unclear (not stated as IT, facility, grid or thermal). Never summed.
    • Other 290 MW: Basis unclear (not stated as IT, facility, grid or thermal). Never summed.

Method: capacity rules. Company-wide investment, area figures and third-party market estimates are never included in these sums.

Hyperscaler and AI cloud activity in Norway

2 tracked projects in Norway, of which 2 involve a hyperscaler or AI cloud as owner, operator, developer or a stated or reported tenant. Part of the Europe, Middle East and Africa (EMEA) region on the hyperscaler and cloud hub.

Hyperscaler and AI cloud projects in Norway
ProjectStageOperator, developer or ownerHyperscaler or AI tenantAnnouncedExpected
Google Skien data centre (Gromstul, Telemark)
Telemark
Under constructionGooglenot stated2024-02-072026
Stargate Norway (Kvandal, Narvik)
Nordland
AnnouncedNscale, AkerOpenAI (officially stated)2025-07-31not stated

Capacity, forecasts and market share: Norway

Every number is shown as published, with its basis, date and source. Figures with different bases (IT power, grid connection, electricity use) or from different sources are never added or blended. Where no figure exists we say not publicly reported. CoolPower makes no forecasts of its own.

Current capacity and pipeline

Current capacity and pipeline, Norway
FigureWhat it measuresStatePeriod or as ofSource
3 TWh
Official source
Electricity use
Data centre electricity consumption in Norway, NVE
Source statement (paraphrased): "3 TWh in 2025"
Operational2025NVE (Norwegian Water Resources and Energy Directorate) (opens in a new tab)
Published 2026. Accessed 19 Oct 2026.
about 10 GW
Official source
Grid requests
Data centre capacity reserved or queued in the Statnett transmission grid, as reported by NVE
Source statement (paraphrased): "about 10 GW reserved and queued"
Requested2026NVE (Norwegian Water Resources and Energy Directorate) (opens in a new tab)
Published 2026. Accessed 19 Oct 2026.

Forecasts and scenarios

Published forecasts, Norway
FigureWhat it measuresPeriod or as ofSource
about 8 TWh
Forecast
Electricity use
NVE forecast of data centre electricity consumption
Source statement (paraphrased): "about 8 TWh in 2030"
2030NVE (Norwegian Water Resources and Energy Directorate) (opens in a new tab)
Published 2026. Accessed 19 Oct 2026.
NVE (Norwegian Water Resources and Energy Directorate), Operational, 2025: 3 TWh. NVE (Norwegian Water Resources and Energy Directorate), forecast, 2030: about 8 TWh. Bars are separate published figures and are not added together.NVE: Electricity use, operational, 20253 TWhNVE: Electricity use, forecast, 2030about 8 TWh
TWh. Solid bars: current. Lighter bars: pipeline. Dashed outline bars: forecasts or scenarios. A range is drawn from its low to its high end. The data table is above.
NVE (Norwegian Water Resources and Energy Directorate), Requested, 2026: about 10 GW. Bars are separate published figures and are not added together.NVE: Grid requests, requested, 2026about 10 GW
GW. Solid bars: current. Lighter bars: pipeline. Dashed outline bars: forecasts or scenarios. A range is drawn from its low to its high end. The data table is above.

Cloud market share

Provider market share: not publicly reported. No public provider market share by country was found except mainland China (Omdia via DCD). Every other country page shows not publicly reported.

Download these 3 figures as CSV All market figures (CSV)

Cloud regions in Norway

A cloud region is a provider's service area. It is not a data centre campus and has no MW figure here.

No cloud regions recorded.

Policy timeline

No policy records published.

Operators and developers

Sources (3), last checked 19 Oct 2026
  1. NVE rapport 17/2026 on data centres and electricity demand (opens in a new tab), NVE (Norwegian Water Resources and Energy Directorate), published 2026, accessed 19 Oct 2026
  2. Nscale, Aker and OpenAI to establish Stargate Norway (opens in a new tab), Aker ASA (Cision), published 31 Jul 2025, accessed 19 Oct 2026
  3. Google starter bygging av et nytt datasenter i Skien, investerer 600 millioner euro (opens in a new tab), Google Norge (NTB press release), published 7 Feb 2024, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.