AWS Project Rainier campus (New Carlisle, Indiana)

OperatingUnited StatesIndiana

Indiana announced in April 2024 that AWS plans to invest USD 11 billion in a data centre campus at New Carlisle. CNBC reported in October 2025 that the site, known as Project Rainier, was operating for Anthropic on 1,200 acres with seven buildings online and a full plan of 30 buildings. IEDC incentives include up to USD 18.3 million in headcount-based tax credits and up to USD 55 million in Hoosier Business Investment tax credits.

Reported figures

Reported figures for AWS Project Rainier campus (New Carlisle, Indiana)
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
USD 11 billion
Official source
11,000,000,000 USD
Investment
Planned investment in USD billions
Source wording: "$11B"
Announced
Stage stated in source: Announced
campus
25 Apr 2024
No. Marked not summable by research: Planned investment in USD billionsiedc.in.gov (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

What changed

  1. 29 Oct 2025 Seven buildings online, reported by CNBC Third-party reported cnbc.com (opens in a new tab)
Sources (2), last checked 19 Oct 2026
  1. Gov. Holcomb announces Amazon Web Services plans to invest $11B to create a new data center campus in Northern Indiana (opens in a new tab), Indiana Economic Development Corporation, published 25 Apr 2024, accessed 19 Oct 2026
  2. Amazon opens $11 billion AI data center Project Rainier in Indiana (opens in a new tab), CNBC, published 29 Oct 2025, accessed 19 Oct 2026

Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.