Project record, campus

Stargate UAE AI infrastructure cluster (1 GW)

Under constructionAbu Dhabi

1 GW AI infrastructure cluster developed by Khazna Data Centers, a G42 company, inside the UAE-US AI Campus. Announced in May 2025 with OpenAI, Oracle, NVIDIA, Cisco and SoftBank as partners. In October 2025 G42 said design and civil works were well advanced, all long-lead equipment had been procured and first mechanical deliveries had arrived. Reuters describes it as a $30 billion first phase of the wider campus.

Part of UAE-US AI Campus (Abu Dhabi). Capacity roll-ups count the parent figure and do not add this record again.

Reported figures

Reported figures for Stargate UAE AI infrastructure cluster (1 GW)
FigureWhat it measuresDelivery stateScope and dateUsed in totalsSource
1 GW
Official source
Otherbasis unclear
Cluster capacity in GW. Basis not defined. Parent campus 5 GW includes it.
Source wording: "a 1GW large-scale AI infrastructure cluster"
Announced
Stage stated in source: Announced
campus
16 Oct 2025
No. Basis unclear (not stated as IT, facility, grid or thermal). Never summed.wam.ae (opens in a new tab)
USD 30 billion
Third-party reported
30,000,000,000 USD
Investment
USD billions as reported by Reuters. Not confirmed by G42 in sources reviewed.
Source wording: "a $30-billion, 1-gigawatt compute cluster known as Stargate UAE"
Announced
Stage stated in source: Announced
campus
11 Sept 2026
No. Marked not summable by research: USD billions as reported by Reuters. Not confirmed by G42 in sources reviewed.internazionale.it (opens in a new tab)

Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.

What changed

  1. 11 Sept 2026 UAE reportedly reworks 5 GW AI campus into distributed sites: Reuters reported, citing anonymous sources, that the UAE is revising its single-site Abu Dhabi AI campus after the Iran conflict, toward a network of protected and partly underground sites. Stargate UAE's first 200 MW was still described as due in 2026. Third-party reported Related: UAE-US AI Campus (Abu Dhabi), Stargate UAE first 200 MW, Khazna Data Centers. internazionale.it (opens in a new tab)wam.ae (opens in a new tab)
  2. 16 Oct 2025 Construction progress update by G42 Related: Khazna Data Centers, Oracle, Stargate UAE first 200 MW. wam.ae (opens in a new tab)

Phases and buildings

Sources (2), last checked 18 Oct 2026
  1. G42 advances construction of Stargate UAE AI infrastructure cluster (opens in a new tab), Emirates News Agency (WAM), published 16 Oct 2025, accessed 18 Oct 2026
  2. Reuters wire (syndicated): UAE revises AI data center plan (opens in a new tab), Internazionale (Reuters syndication), published 11 Sept 2026, accessed 18 Oct 2026

Last checked 18 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.