NED Netanya I data centre
NED Data Centers lists Netanya I with 16 MVA of a planned 60 MVA in the first phase, 10.5 MW of IT and ready for service in Q4 2026. NED lists 3,600 square metres of white space, a floor load of 1,500 kg per square metre, direct liquid cooling with dedicated piping for CDUs and a backup utility feed of 16 MVA. It describes a fortified underground facility 400 m from an IEC substation, about 20 km from Tel Aviv, with 72 hours of autonomous operation and a LEED Gold target.
Reported figures
| Figure | What it measures | Delivery state | Scope and date | Used in totals | Source |
|---|---|---|---|---|---|
| 10.5 MW Official source | IT power IT power, first phase Source wording: "10.5 MW IT" | Planned Stage stated in source: Under construction | campus date not given, seen 19 Oct 2026 | No. Marked not summable by research: IT power, first phase | ned-dc.com (opens in a new tab) |
Each figure is shown as reported, with its own definition. IT, facility, grid and thermal figures are never added together. Capacity definitions.
Sources (1), last checked 19 Oct 2026
- Project Netanya I (opens in a new tab), NED Data Centers, accessed 19 Oct 2026
Last checked 19 Oct 2026 by CoolPower Index research (automated, sourced). Report a correction.