Projects and operators

Data centre projects

121 published campus, phase and building records. Each figure keeps its own metric class, stage and source. Filters update the address bar so you can share a view.

Also see operators and cloud regions. A cloud region is not a campus.

121 of 121 projects

Data centre projects
ProjectCountryStageLevelKey reported figureOperator, developer or ownerLatest change
Abilene AI campus at Lancium Clean Campus (Stargate Abilene, Texas)United States
Texas
Under constructioncampus1.2 GWAnnouncedCrusoe, Lancium18 Mar 2025: Phase two construction started (six buildings)
Abilene AI campus phase 1 (two buildings)
Part of Abilene AI campus at Lancium Clean Campus (Stargate Abilene, Texas)
United States
Texas
Under constructionphaseat least 200 MWUnder constructionCrusoe18 Mar 2025: Phase two construction started (six buildings)
Africa Data Centres Egypt (Vodafone Business, Elsewedy Electric, Cassava Technologies)Egypt
Egypt
Announcedcampusnot disclosedAfrica Data Centresnot disclosed
AirTrunk JHB1 (Johor Bahru)Malaysia
Johor
Operatingcampusat least 150 MWDesign or ultimate capacityAirTrunknot disclosed
AirTrunk JHB2 (Iskandar Puteri, Johor)Malaysia
Johor
Announcedcampusat least 270 MWAnnouncedAirTrunk12 Feb 2025: Announced by AirTrunk
Amazon Falls Township innovation campus (Bucks County, Pennsylvania)United States
Pennsylvania
Under constructioncampusat least USD 20 billionInvestmentAmazon Web Services (AWS)not disclosed
Aruba Hyper Cloud Data Center campus (Tecnopolo Tiburtino, Rome)Italy
Lazio
Operatingcampus30 MWPlannedArubanot disclosed
Atman WAW-3 data centre campus (Warsaw)Poland
Masovia
Operatingcampus14.4 MWOperatingAtmannot disclosed
AWS data centre complexes (Madison County, Mississippi)United States
Mississippi
Under constructionprojectUSD 10 billionInvestmentAmazon Web Services (AWS)not disclosed
AWS data centre land option at Tnuvot (near Netanya)Israel
Central District
Announcedcampusnot disclosedAmazon Web Services (AWS)not disclosed
AWS Europe (Milan) Region expansion (investment programme)Italy
Lombardy
Announcedprojectat least EUR 1.2 billionInvestmentAmazon Web Services (AWS)not disclosed
AWS Europe (Spain) Region data centres in Aragón (investment programme)Spain
Aragón
AnnouncedprojectEUR 33.7 billionInvestmentAmazon Web Services (AWS)not disclosed
AWS innovation campus (Richmond County, North Carolina)United States
North Carolina
AnnouncedprojectUSD 10 billionInvestmentAmazon Web Services (AWS)not disclosed
AWS Middle East (Saudi Arabia) Region data centresSaudi Arabia
Saudi Arabia
Under constructionprojectat least USD 5.3 billionInvestmentAmazon Web Services (AWS)not disclosed
AWS Project Rainier campus (New Carlisle, Indiana)United States
Indiana
OperatingcampusUSD 11 billionInvestmentAmazon Web Services (AWS)29 Oct 2025: Seven buildings online, reported by CNBC
Bell AI data centre with Thompson Rivers University (Kamloops)Canada
British Columbia
Under constructioncampusnot disclosedBell Canadanot disclosed
Bell AI Fabric and Groq inference facility (Kamloops, British Columbia)Canada
British Columbia
Operatingcampusnot disclosedBell Canadanot disclosed
Brookfield AI data centre campus (Strängnäs)Sweden
Södermanland
Delayedcampusup to SEK 95 billionInvestmentBrookfield16 Mar 2026: SVT reports power supply unresolved and other sites under study
Campus IA (Fouju, Seine-et-Marne)France
Île-de-France
Planningcampus240 MWPlannedCampus IAnot disclosed
Culham AI Growth Zone data centre (Oxfordshire)United Kingdom
South East England
Planningcampusnot disclosedUK Atomic Energy Authority (UKAEA)not disclosed
Data4 and Brookfield e-Valley AI campus (Cambrai, former Air Base 103)France
Hauts-de-France
Planningcampusabout EUR 10 billionInvestmentData4, Brookfield19 Oct 2026: Second land approval reported
Data4 MIL02 campus (Vittuone, Milan)Italy
Lombardy
Under constructioncampusEUR 500 millionInvestmentData4not disclosed
Data4 Warsaw campus (Jawczyce, Ożarów Mazowiecki)Poland
Masovia
Operatingcampusup to 60 MWPlannedData49 Apr 2026: Second data centre inaugurated
DataVita and CoreWeave Lanarkshire AI Growth Zone (Airdrie)United Kingdom
Scotland
Announcedcampusnot disclosedDataVitanot disclosed
DataVolt Oxagon AI data centre campus (NEOM)Saudi Arabia
Tabuk Province (NEOM)
Under constructioncampusnot disclosedDataVolt31 Aug 2026: Construction started on first phase
DataVolt Oxagon phase 1 (360 MW, incl. 100 MW with HUMAIN)
Part of DataVolt Oxagon AI data centre campus (NEOM)
Saudi Arabia
Tabuk Province (NEOM)
Under constructionphasenot disclosedDataVolt, HUMAIN31 Aug 2026: Construction started on first phase
Deutsche Telekom Industrial AI Cloud (Tucherpark, Munich)Germany
Bavaria
Operatingcampusnot disclosedDeutsche Telekomnot disclosed
Digital Realty DC-CFA2 data centre (Jurong Island, Singapore)Singapore
Jurong Island
Provisional capacity allocationproject50 MWProvisional allocationDigital Realty21 Aug 2026: EDB and IMDA provisionally allocated 50 MW each to Digital Realty, Equinix, Keppel Data Centres and STT GDC under the second Data Centre Call for Application. Winners committed to at least 50% green energy pathways, liquid cooling, Green Mark Platinum and efficient IT.
Echelon DUB20 data centre (Arklow, Co Wicklow)Ireland
Wicklow
Under constructioncampusEUR 4.2 billionInvestmentEchelon Data Centresnot disclosed
EcoDataCenter 2 campus (Kvarnsveden, Borlänge)Sweden
Dalarna
Under constructioncampus250 MWPlannedEcoDataCenternot disclosed
Equinix DB7x (Blanchardstown, Dublin)Ireland
Fingal, Dublin
Under constructionbuildingUSD 92 millionInvestmentEquinix20 Mar 2026: Construction started
Equinix DC-CFA2 data centre (Jurong Island, Singapore)Singapore
Jurong Island
Provisional capacity allocationproject50 MWProvisional allocationEquinix21 Aug 2026: EDB and IMDA provisionally allocated 50 MW each to Digital Realty, Equinix, Keppel Data Centres and STT GDC under the second Data Centre Call for Application. Winners committed to at least 50% green energy pathways, liquid cooling, Green Mark Platinum and efficient IT.
Equinix Hertfordshire campus (South Mimms)United Kingdom
East of England
Permittedcampusnot disclosedEquinixnot disclosed
Equinix LG3 (Lagos)Nigeria
Lagos State
AnnouncedcampusUSD 22 millionInvestmentEquinixnot disclosed
Eshkol data centre site (north of Ashdod Port)Israel
Southern District
Planningcampusup to 250 MWPlannedServerfarm, Dalia Energy25 Aug 2026: Dalia Energy takes 50%, licence freeze of 140 days reported
Fluidstack AI data centre at Bosquel Business Park (withdrawn)France
Somme (Hauts-de-France)
Cancelledcampusnot disclosednot disclosed20 Mar 2026: Fluidstack reported to withdraw from French projects
Google AI hub (Visakhapatnam)India
Andhra Pradesh
Under constructioncampusabout USD 15 billionInvestmentGoogle, AdaniConneX, Nxtra by Airtel28 Apr 2026: Groundbreaking at Tarluvada
Google Cloud and PIF AI hub (Dammam region expansion)Saudi Arabia
Eastern Province
AnnouncedcampusUSD 10 billionInvestmentGooglenot disclosed
Google Dietzenbach data centre (Hesse)Germany
Hesse
AnnouncedbuildingEUR 5.5 billionInvestmentGoogle11 Nov 2025: Announced with heat recovery partnership
Google Dorchester County data centre sites (South Carolina)United States
South Carolina
Under constructioncampusUSD 9 billionInvestmentGooglenot disclosed
Google Eemshaven data centre campus (Groningen)Netherlands
Groningen
OperatingcampusEUR 600 millionInvestmentGooglenot disclosed
Google Elmina data centre (Selangor)Malaysia
Selangor
Under constructionbuildingUSD 2 billionInvestmentGoogle20 Aug 2026: Operations expected within about nine months
Google Farciennes data centre campus (Hainaut)Belgium
Hainaut (Wallonia)
DelayedcampusUSD 1 billionInvestmentGoogle16 Aug 2026: Sambre water pumping permit refused
Google Fredericia data centre (Jutland)Denmark
Southern Denmark
OperatingcampusEUR 600 millionInvestmentGooglenot disclosed
Google Grange Castle data centre extension (phase 3, Dublin)Ireland
South Dublin
Permittedphase72,400 sq mPermittedGoogle28 Sept 2026: An Coimisiún Pleanála granted permission for a 72,400 sq m extension at Google's Grange Castle campus after the council refused it in 2024, with conditions on PPAs and renewable backup fuel.
Google Groningen Westpoort data centre (fourth Dutch site)Netherlands
Groningen
Under constructioncampusat least EUR 600 millionInvestmentGooglenot disclosed
Google Hamina data centre campusFinland
Kymenlaakso
OperatingcampusEUR 1 billionInvestmentGoogle18 May 2026: Heat recovery plant supplying district heating since Q4 2025
Google Kajaani data centre (Kainuu)Finland
Kainuu
On holdcampusnot disclosedGoogle6 Oct 2026: Agency orders halt to preparatory work pending environmental assessment
Google Kronstorf data centre (Upper Austria)Austria
Upper Austria
Under constructioncampusnot disclosedGooglenot disclosed
Google Middenmeer data centreNetherlands
North Holland
OperatingcampusEUR 500 millionInvestmentGooglenot disclosed
Google Muhos data centre (North Ostrobothnia)Finland
North Ostrobothnia
On holdcampusnot disclosedGoogle6 Oct 2026: Agency orders halt to preparatory work pending environmental assessment
Google Saint-Ghislain data centre campusBelgium
Hainaut (Wallonia)
OperatingcampusEUR 5 billionInvestmentGooglenot disclosed
Google Skien data centre (Gromstul, Telemark)Norway
Telemark
Under constructioncampus240 MWPlannedGooglenot disclosed
Google Stillwater data centre campus (Oklahoma)United States
Oklahoma
AnnouncedcampusUSD 9 billionInvestmentGoogle20 Nov 2025: Two Muskogee County campuses announced
Google Waltham Cross data centre (Hertfordshire)United Kingdom
Hertfordshire, England
OperatingbuildingGBP 5 billionInvestmentGoogle16 Sept 2025: Data centre opened
Google West Memphis data centre (Crittenden County, Arkansas)United States
Arkansas
Under constructioncampusUSD 4 billionInvestmentGooglenot disclosed
Google Winschoten data centre (third Dutch site)Netherlands
Groningen
OperatingcampusEUR 600 millionInvestmentGooglenot disclosed
iXAfrica NBOX1 campus (Nairobi)Kenya
Nairobi
Operatingcampus4.5 MWiXAfricanot disclosed
Kasi LOS1 data centre (Lagos)Nigeria
Lagos State
Commissionedcampusnot disclosedKasi Cloud19 May 2026: LOS1 launched
Keppel Data Centres DC-CFA2 data centre (Jurong Island, Singapore)Singapore
Jurong Island
Provisional capacity allocationproject50 MWProvisional allocationKeppel Data Centres21 Aug 2026: EDB and IMDA provisionally allocated 50 MW each to Digital Realty, Equinix, Keppel Data Centres and STT GDC under the second Data Centre Call for Application. Winners committed to at least 50% green energy pathways, liquid cooling, Green Mark Platinum and efficient IT.
Khazna and Benya data centre (Maadi Technology Park, Cairo)Egypt
Cairo
Not disclosedcampus25 MWPlannedKhazna Data Centersnot disclosed
Khazna AUH4 data centre (Mafraq, Abu Dhabi)United Arab Emirates
Abu Dhabi
Under constructioncampusnot disclosedKhazna Data Centersnot disclosed
Khazna AUH8 data centre (Masdar City, Abu Dhabi)United Arab Emirates
Abu Dhabi
Under constructioncampusUSD 300 millionInvestmentKhazna Data Centersnot disclosed
Khazna QAJ1 AI data centre (Ajman)United Arab Emirates
Ajman
Announcedcampusnot disclosedKhazna Data Centersnot disclosed
Lambda AI factory (Kansas City, Missouri)United States
Missouri
Under constructioncampusnot disclosedLambdanot disclosed
Meta data centre campus (Talavera de la Reina)Spain
Castilla-La Mancha
PlanningcampusEUR 750 millionInvestmentMeta Platforms11 Aug 2026: Regional government approves land reparcelling
Meta Odense data centre (Funen)Denmark
Southern Denmark
Operatingcampusat least DKK 10 billionInvestmentMeta Platforms14 Dec 2022: Further Odense projects halted
Meta Richland Parish data center (Hyperion, Louisiana)United States
Louisiana
Under constructioncampusat least USD 50 billionInvestmentMeta Platforms13 Jul 2026: Meta said its Louisiana site, home of the Hyperion cluster, will grow to 5 GW of compute capacity with more than $50 billion invested, naming DPR, Turner and Mortenson as general contractors.
Meta Rosemount data center (Minnesota)United States
Minnesota
Under constructioncampusat least USD 800 millionInvestmentMeta Platformsnot disclosed
Meta Zeewolde data centre (cancelled)Netherlands
Flevoland
Cancelledcampusnot disclosedMeta Platforms1 Jul 2022: Project officially cancelled
Microsoft and G42 geothermal data centre (Olkaria)Kenya
Nakuru County
Delayedcampusnot disclosedMicrosoft, G429 May 2026: Government says reports of suspension are incorrect
Microsoft Austria cloud region data centres (Schwechat, Achau, Vösendorf area)Austria
Lower Austria
OperatingcampusEUR 1 billionInvestmentMicrosoft30 Jun 2025: Cloud region inaugurated, services from August 2025
Microsoft Belgium Central cloud region data centresBelgiumOperatingcampusnot disclosedMicrosoft18 Nov 2025: Belgium Central region opened
Microsoft Canada Central and Canada East region expansionCanada
Ontario and Quebec
Under constructionprojectCAD 19 billionInvestmentMicrosoftnot disclosed
Microsoft data centre (Bornasco, Pavia)Italy
Lombardy
Under constructioncampusnot disclosedMicrosoft5 Feb 2026: Construction under way
Microsoft data centre campuses in Aragón (La Muela, Villamayor de Gállego, Zaragoza)Spain
Aragón
Planningcampusat least EUR 5.3 billionInvestmentMicrosoftnot disclosed
Microsoft data centres at Hepokorpi (Espoo) and Kolabacken (Kirkkonummi)Finland
Uusimaa
Not disclosedcampusnot disclosedMicrosoft6 May 2026: Fortum heat plants at both sites start operating
Microsoft Denmark East datacenter region campuses (Høje Taastrup, Køge, Roskilde)Denmark
Zealand
Operatingcampusnot disclosedMicrosoft26 Mar 2026: Denmark East region officially opened
Microsoft DUB14 and DUB15 (Grange Castle, Dublin)Ireland
Dublin
Permittedcampusnot disclosedMicrosoft21 Jul 2026: Extension of duration of permission granted
Microsoft Fairwater 1 (Mount Pleasant, Wisconsin)
Part of Microsoft Mount Pleasant campus (Fairwater, Wisconsin)
United States
Wisconsin
Operatingphase1,200,000 sq ftOperatingMicrosoft23 Jun 2026: Microsoft said the first Mount Pleasant facility was fully operational on 23 June 2026, with a second facility due in 2028. The site uses closed-loop liquid cooling for over 90% of capacity.
Microsoft Mount Pleasant campus (Fairwater, Wisconsin)United States
Wisconsin
Under constructioncampusUSD 4.7 billionInvestmentMicrosoft23 Jun 2026: Microsoft said the first Mount Pleasant facility was fully operational on 23 June 2026, with a second facility due in 2028. The site uses closed-loop liquid cooling for over 90% of capacity.
Microsoft Poland data centre expansion (Poland Central region)Poland
Masovia
Announcedprojectabout PLN 3 billionInvestmentMicrosoftnot disclosed
Microsoft Qatar Central cloud region data centresQatar
Doha
Operatingcampusnot disclosedMicrosoftnot disclosed
Microsoft Rhenish mining area data centre cluster (Bergheim, Bedburg, Elsdorf)Germany
North Rhine-Westphalia
Under constructioncampusEUR 3.2 billionInvestmentMicrosoft12 Mar 2026: Groundbreaking in Bergheim, permits for Bergheim and Bedburg
Microsoft second Mount Pleasant facility (Wisconsin)
Part of Microsoft Mount Pleasant campus (Fairwater, Wisconsin)
United States
Wisconsin
Under constructionphasenot disclosedMicrosoft23 Jun 2026: Microsoft said the first Mount Pleasant facility was fully operational on 23 June 2026, with a second facility due in 2028. The site uses closed-loop liquid cooling for over 90% of capacity.
Microsoft South Africa cloud and AI infrastructure expansionSouth Africa
Gauteng and Western Cape
AnnouncedprojectZAR 5.4 billionInvestmentMicrosoftnot disclosed
Microsoft Sweden Central data centres (Gävle, Sandviken, Staffanstorp)Sweden
Gävleborg and Skåne
OperatingcampusSEK 33.7 billionInvestmentMicrosoftnot disclosed
Mistral AI compute cluster at Eclairion (Bruyères-le-Châtel, Essonne)France
Île-de-France
Under constructioncampusnot disclosedEclairionnot disclosed
Nebius and DataOne AI data centre (Vineland, New Jersey)United States
New Jersey
Under constructioncampusnot disclosedDataOne8 Sept 2025: Multi-year Microsoft capacity agreement for Vineland
Nebius Mäntsälä data centre (first site)Finland
Uusimaa
Operatingcampusnot disclosedNebiusnot disclosed
Nebius second Mäntsälä data centreFinland
Uusimaa
Under constructioncampus70 MWPlannedNebiusnot disclosed
NED Netanya I data centreIsrael
Central District
Under constructioncampus10.5 MWPlannedNED Data Centersnot disclosed
NEXTDC S7 data centre (Eastern Creek, Sydney)Australia
New South Wales
Planningcampusnot disclosedNEXTDCnot disclosed
Nscale Loughton AI data centre (Essex)United Kingdom
Essex, England
Delayedprojectup to 90 MWAnnouncedNscale18 Oct 2026: Reuters and the Guardian, citing the Telegraph, reported on 18 October 2026 that Microsoft ended its agreement for Nscale's planned AI data centre at Loughton, Essex. A month earlier the Guardian reported UK Power Networks might not supply enough power until the early to mid 2030s, against a 2027 target. Nscale says it is pursuing alternative power.
OADC LOS1 (Lagos)Nigeria
Lagos
Under constructioncampusnot disclosedOpen Access Data Centres (OADC)not disclosed
ODATA QR03 (Querétaro)Mexico
Querétaro
Operatingcampus72 MWOperatingODATAnot disclosed
Omnia data centre at the Pecém complex (Caucaia, Ceará)Brazil
Ceará
Under constructioncampusnot disclosedOmnia10 Sept 2026: Prosecutors seek to block operation pending impact study
QTS Cambois campus phase 1 (two data halls)
Part of QTS Cambois data centre campus (Blyth, Northumberland)
United Kingdom
Northumberland, England
Permittedphasenot disclosedQTS Data Centers, Blackstone2 Dec 2025: Phase 1 reserved matters (two data halls) approved
QTS Cambois data centre campus (Blyth, Northumberland)United Kingdom
Northumberland, England
Under constructioncampusGBP 10 billionInvestmentQTS Data Centers, Blackstone2 Dec 2025: Phase 1 reserved matters (two data halls) approved
QTS Proyecto Rhodes data centre campus (Calatorao, Zaragoza)Spain
Aragón
Permittedcampus650 MWPlannedQTS Data Centers, Blackstone30 Sept 2026: Partial final approval of the general interest plan
Rack Centre LGS2 (Lagos)Nigeria
Lagos
Operatingcampusnot disclosedRack Centrenot disclosed
Scala AI City (Eldorado do Sul)Brazil
Rio Grande do Sul
Announcedcampusnot disclosedScala Data Centersnot disclosed
Schwarz Digits AI data centre (Lübbenau, Brandenburg)Germany
Brandenburg
Under constructioncampusabout 200 MWPlannedSchwarz Digitsnot disclosed
SoftBank AI data centre at the former Sharp Sakai plant (Osaka)Japan
Osaka Prefecture
Announcedcampusnot disclosedSoftBanknot disclosed
ST Telemedia Global Data Centres DC-CFA2 data centre (Jurong Island, Singapore)Singapore
Jurong Island
Provisional capacity allocationproject50 MWProvisional allocationST Telemedia Global Data Centres21 Aug 2026: EDB and IMDA provisionally allocated 50 MW each to Digital Realty, Equinix, Keppel Data Centres and STT GDC under the second Data Centre Call for Application. Winners committed to at least 50% green energy pathways, liquid cooling, Green Mark Platinum and efficient IT.
Stargate campus, Saline Township (Michigan)United States
Michigan
Announcedcampusnot disclosedRelated Digitalnot disclosed
Stargate Norway (Kvandal, Narvik)Norway
Nordland
Announcedcampusnot disclosedNscale, Akernot disclosed
Stargate site, Doña Ana County (New Mexico)United States
New Mexico
Announcedcampusnot disclosednot disclosednot disclosed
Stargate site, Lordstown (Ohio)United States
Ohio
Under constructioncampusnot disclosedSoftBanknot disclosed
Stargate site, Milam County (Texas)United States
Texas
Announcedcampusnot disclosedSoftBanknot disclosed
Stargate site, Shackelford County (Texas)United States
Texas
Announcedcampusnot disclosednot disclosednot disclosed
Stargate UAE AI infrastructure cluster (1 GW)
Part of UAE-US AI Campus (Abu Dhabi)
United Arab Emirates
Abu Dhabi
Under constructioncampusUSD 30 billionInvestmentKhazna Data Centers11 Sept 2026: Reuters reported, citing anonymous sources, that the UAE is revising its single-site Abu Dhabi AI campus after the Iran conflict, toward a network of protected and partly underground sites. Stargate UAE's first 200 MW was still described as due in 2026.
Stargate UAE first 200 MW
Part of Stargate UAE AI infrastructure cluster (1 GW)
United Arab Emirates
Abu Dhabi
Under constructionphasenot disclosedKhazna Data Centers11 Sept 2026: Reuters reported, citing anonymous sources, that the UAE is revising its single-site Abu Dhabi AI campus after the Iran conflict, toward a network of protected and partly underground sites. Stargate UAE's first 200 MW was still described as due in 2026.
Stargate UK site at Cobalt Park (North Tyneside)United Kingdom
North East England
Announcedcampusnot disclosedNscalenot disclosed
Syntys (Q Data) data centres hosting Ooredoo sovereign AI cloudQatar
Doha
Operatingcampusnot disclosedSyntysnot disclosed
Teraco CT2 (Cape Town)South Africa
Western Cape
Operatingcampus50 MWTeraconot disclosed
Teraco JB7 (Isando campus, Ekurhuleni)South Africa
Gauteng
Under constructioncampus40 MWUnder constructionTeraconot disclosed
UAE-US AI Campus (Abu Dhabi)United Arab Emirates
Abu Dhabi
Under constructioncampusnot disclosedG4211 Sept 2026: Reuters reported, citing anonymous sources, that the UAE is revising its single-site Abu Dhabi AI campus after the Iran conflict, toward a network of protected and partly underground sites. Stargate UAE's first 200 MW was still described as due in 2026.
Vantage Data Centers Warsaw campus (WAW1)Poland
Masovia
Operatingcampus48 MWPlannedVantage Data Centersnot disclosed
Vantage DUB11 Profile Park campus (Clondalkin, Dublin)Ireland
South Dublin
Delayedcampus52 MWUnder constructionVantage Data Centers24 Jul 2026: Filings show €151.7m impairment for delayed delivery
xAI Colossus supercomputer (Memphis, Tennessee)United States
Tennessee
Operatingcampus150 MWxAInot disclosed

Capacity in tracked public coverage

Tracked public coverage, not a national total. Sums of reported, project-level figures from 9 of the 121 published project records we track for all published project records. Each metric and each delivery class is summed on its own and never added to another. Confirmed operating capacity never includes design or ultimate capacity. Delayed projects are never counted as under construction now. Campus and phase figures are not double counted. Ranges and upper bounds are not summed. Unknown values are not counted as zero.

MetricDelivery classSum of tracked recordsContributing records
InvestmentReported project investment
Project-level investment in one currency. Components of a total are not added again. Company-wide programmes are excluded.
USD 92 million
IT powerProvisional capacity allocation
Capacity provisionally allocated by an authority. This is not planning permission and not built capacity.
200 MW
IT powerAnnounced or design capacity (not delivered)
Ultimate, design or announced capacity. Not delivered capacity. Never added to confirmed figures.
at least 420 MW
Includes a lower-bound figure, so the sum is a minimum.
IT powerDelayed or on hold (current stage)
Projects currently delayed or on hold, with the capacity they were reported to deliver.
52 MW
Total facility powerAnnounced or design capacity (not delivered)
Ultimate, design or announced capacity. Not delivered capacity. Never added to confirmed figures.
1,200 MW
Figures not counted (129) and why

Method: capacity rules. Company-wide investment, area figures and third-party market estimates are never included in these sums.