DC Explorer: system archetype

Brownfield liquid-cooling retrofit

An operating air-cooled hall adds liquid-cooled racks. CDUs connect either to the existing chilled-water system or reject heat to room air, within the limits of the existing electrical, structural and plant capacity.

Draft conceptual topology, not yet engineering-reviewed. It shows which systems connect, not capacities, quantities, redundancy or a design. It is not a single-line diagram or a schematic, and it does not show that any products are compatible. Updated 18 Oct 2026.

When to use it: Use it to plan the questions an operating site must answer before adding high-density racks.

System graph

Lines show what feeds what: electrical heat network controls and services. Select a box to jump to its entry. The 3D explorer shows the same systems.

Systems and connections

Electrical

Thermal

IT and network

  • Racks and rack power (PDUs or power shelves)

    Hold IT equipment and distribute power inside the rack. Rack density and weight drive floor, power and cooling requirements.

    Fed by: UPS and batteries (UPS-backed IT supply)

    Feeds: Servers and accelerators (rack power)

    On CoolPower Index: Direct liquid cooling (direct-to-chip), 800 VDC rack power

    Open in 3D: Racks and rack power (PDUs or power shelves)

  • Servers and accelerators

    Turn nearly all of their electrical input into heat at the IT boundary. Power and cooling needs depend on the exact model and configuration.

    Fed by: Racks and rack power (PDUs or power shelves) (rack power)

    Feeds: Network switches and optics (data), Cold plates on new racks (processor heat), Existing CRAHs (residual air heat)

    On CoolPower Index: Direct liquid cooling (direct-to-chip)

    Open in 3D: Servers and accelerators

  • Network switches and optics

    Connect servers, storage and the outside world. Network power and cabling are often missed in early estimates.

    Fed by: Servers and accelerators (data), Storage (data)

    On CoolPower Index: No verified portal record linked yet.

    Open in 3D: Network switches and optics

  • Storage

    Holds data for the workload. Configuration, usable capacity and power vary widely.

    Feeds: Network switches and optics (data)

    On CoolPower Index: No verified portal record linked yet.

    No 3D model for this system yet.

Context

  • Controls and monitoring (BMS, EPMS, DCIM)

    Coordinates plant, alarms and metering. Interfaces and sequences must be specified and commissioned.

    On CoolPower Index: No verified portal record linked yet.

    No 3D model for this system yet.

  • Fire safety, leak detection and water treatment

    Detection, suppression, leak sensing and fluid quality management. Requirements depend on local codes and the fluids used.

    Feeds: CDU (liquid-to-liquid or liquid-to-air) (leak detection near live IT)

    On CoolPower Index: No verified portal record linked yet.

    No 3D model for this system yet.

  • Commissioning and service access

    Testing against the design intent, plus space and procedures to maintain equipment without unplanned outages.

    Feeds: CDU (liquid-to-liquid or liquid-to-air) (tie-in and flushing during operation)

    On CoolPower Index: No verified portal record linked yet.

    No 3D model for this system yet.

Size it

The archetype has no built-in numbers. Use the engineering pack to work out load, heat, rack, CDU and flow figures from your own assumptions. Both are saved in the same brief.

Sources

These references explain system functions. They do not validate this topology. NVIDIA's reference design is one specific design, not a universal pattern to scale.

Other archetypes: Conventional air-cooled colocation, Mixed air and direct liquid cooling, Dense AI liquid-cooled cluster.