Markets & Investment · US power · updated 31 Oct 2026

Flag of United States US data centre power: what the grid charges, who is queuing and what is really connected

PJM capacity auction results by year, the ERCOT large-load queue and utilities' own data centre pipelines, in one place. For engineers sizing power, buyers and consultants judging timelines, and investors following the cost of capacity. Every figure is dated, sourced and labelled Live, Confirmed or Projected.

PJM pricesERCOT queueReally connectedUtility pipelinesNew rulesQuestions

Not investment advice. Prices and pipelines come from grid operators, utilities and named publishers. Forecasts and plans are theirs, shown with their date. We make no forecasts or recommendations.

US data centre power in brief

  • PJM, the grid operator that serves Northern Virginia, cleared its capacity auction at the price cap for three delivery years in a row: US$325.00 per MW-day for June 2028 to May 2029, against US$28.92 for 2024/25.
  • The value of capacity cleared in PJM's auction rose from US$2.2bn for 2024/25 to US$16.4bn for 2028/29 (PJM's own figure). PJM notes this is not the total cost to consumers.
  • In Texas, large loads asking ERCOT to connect grew from 63 GW in December 2024 to about 474 GW by June 2026, about 90% of it data centres. That is more than five times ERCOT's record peak demand.
  • Requests are not demand. Of 9,456 MW of large loads approved to energise in ERCOT, the operator saw a peak of 4,132 MW actually in use in September 2026.
  • Utilities report their own pipelines on different definitions: Dominion over 54 GW of data centre capacity in contracting stages, AEP 84 GW of contracted load through 2031 and Southern Company 17 GW contracted. These are shown side by side, never added up.

Flag of United StatesConfirmed

US$325.00/MW-day

PJM capacity price for 2028/29, cleared at the cap

Source: PJM Interconnection (opens in a new tab)

Flag of United StatesConfirmed

US$16.4bn

value of capacity cleared in PJM's 2028/29 auction, up from US$2.2bn for 2024/25

Source: PJM Interconnection (opens in a new tab)

Flag of United StatesProjected

about 474 GW

large loads asking to connect in Texas (ERCOT), June 2026

Source: Utility Dive (opens in a new tab)

Flag of United StatesLive

4,132 MW

observed in use in September 2026, of 9,456 MW approved to energise in ERCOT

Source: ERCOT (opens in a new tab)

Flag of United StatesProjected

over 54 GW

data centre capacity in Dominion Energy's contracting stages, Q3 2026

Source: The Motley Fool (opens in a new tab)

Flag of United StatesConfirmed

84 GW

AEP contracted load through 2031, up 22% in a quarter

Source: Utility Dive (opens in a new tab)

Understand the numbers

  • Live measured today, such as load actually in use.
  • Confirmed decided or signed, such as an auction result or a contract.
  • Projected asked for, planned or forecast, such as queue requests and pipelines.
US$ per MW-day
What PJM pays a power plant (or a demand response provider) to be available for one megawatt for one day. It is a price for capacity, not for energy used.
Cleared value (US$bn)
PJM's cleared megawatts times the clearing price. A guide to the size of the bill, not the total cost to consumers.
GW requested
What developers have asked a grid to connect. Many requests are duplicates or speculative, so this is not demand.
Contracted or in contracting
Each utility defines these stages itself, so pipelines from different utilities are shown side by side and never added up or ranked.
MW versus TWh
MW is power at a moment. TWh is energy used over a year.

PJM capacity auction results by year

PJM capacity auction clearing price by delivery year (US$ per MW-day) Confirmed · Auction result

RTO-wide Base Residual Auction clearing price for unforced capacity (UCAP). From 2026/27 to 2028/29 the price cleared at a FERC-approved price cap, so the true market price would have been higher. PJM's own simulation without the cap and floor gives US$554.72 for 2028/29. Delivery years run June to May. Darker bars are years that cleared at the cap.

Source: PJM Interconnection: 2028/2029 Base Residual Auction Report (opens in a new tab) Published 14 Jul 2026. Accessed 31 Oct 2026.

Show the data as a table
Delivery year (June to May)US$ per MW-day (UCAP)Note
2018/19US$164.77
2019/20US$100.00
2020/21US$76.53
2021/22US$140.00
2022/23US$50.00
2023/24US$34.13
2024/25US$28.92
2025/26US$269.92
2026/27US$329.17Cleared at the cap
2027/28US$333.44Cleared at the cap
2028/29US$325.00Cleared at the cap
PJM capacity auction: value of cleared capacity by delivery year (US$bn) Confirmed · Auction result

PJM's figure: cleared megawatts times the clearing price in each zone. PJM says it is not the total cost to consumers, because load hedged through self-supply or bilateral contracts does not pay the auction price. Its own simulation with no price cap or floor puts 2028/29 at US$29.7bn. Darker bars are years that cleared at the cap.

Source: PJM Interconnection: 2028/2029 Base Residual Auction Report (opens in a new tab) Published 14 Jul 2026. Accessed 31 Oct 2026.

Show the data as a table
Delivery yearCleared value (US$bn)Note
2018/19US$10.9bn
2019/20US$7.0bn
2020/21US$7.0bn
2021/22US$9.3bn
2022/23US$3.9bn
2023/24US$2.2bn
2024/25US$2.2bn
2025/26US$14.7bn
2026/27US$16.1bnCleared at the cap
2027/28US$16.4bnCleared at the cap
2028/29US$16.4bnCleared at the cap
2028/29 without cap or floor (PJM simulation)US$29.7bnSimulation, not a result

Our commentary (not advice): the capacity bill grew about 7 times in four auctions while the price sat at the cap for the last three, so the cap, not the market, now sets the price. The Independent Market Monitor counted 17,071 MW of existing and forecast data centre load in the forecast behind the 2027/28 auction (Monitoring Analytics (PJM Independent Market Monitor): Analysis of the 2027/2028 RPM Base Residual Auction, Part A (opens in a new tab)). PJM's own simulation without the cap gives US$554.72 per MW-day for 2028/29. More on the money side: Markets & Investment.

Flag of United States Texas: the ERCOT large-load interconnection queue

Texas (ERCOT): large loads asking to connect (GW requested) Projected · Connection requests

Every point is ERCOT's own count of large-load interconnection requests (75 MW or more), as published by ERCOT or reported from its filings. Requests are not a forecast of demand: many are speculative or for the same project at several sites.

Published by ERCOT ERCOT's count as reported by a named outlet. Hover or tap a bar for its own source and date.

Sources, ERCOT first: Dec 2024: ERCOT: Board item 16.2: System Planning and Weatherization Update (large loads as of 18 November 2025) (opens in a new tab); Nov 2025: ERCOT: Board item 16.2: System Planning and Weatherization Update (large loads as of 18 November 2025) (opens in a new tab); Sep 2024: The Texas Tribune: Data center explosion creates planning problems for Texas (opens in a new tab); Oct 2025: The Texas Tribune: Data center explosion creates planning problems for Texas (opens in a new tab); Jun 2026: Utility Dive: Facing an estimated 474 GW of interconnection requests, Texas hits pause on data centers (opens in a new tab). Accessed 31 Oct 2026.

Show the data as a table
ERCOT Batch Zero: how the large-load requests were classified, September 2026 (GW requested) Projected · Conditional classification

Batch Zero is ERCOT's one-time study of large loads that want to connect. Conditional classification issued 3 September 2026, final decisions due in December after the governor's audit. ERCOT's deck gives the studied total as both 125.4 GW (chart) and 127.9 GW (summary). Base load includes some loads that are already energised. The three groups are one set of submissions split by status, so they can be shown together.

Source: ERCOT: Batch Zero Update (board item 14) (opens in a new tab) Published 11 Sept 2026. Accessed 31 Oct 2026.

Show the data as a table
ClassificationGW requestedProjects
Excluded302.2 GW373
Studied load (conditional)125.4 GW158
Base load (conditional)66.4 GW204

What is really connected

ERCOT: approved to energise versus actually in use, September 2026 Live · Measured by ERCOT
Approved to energise9,456 MWObserved in use (peak)4,132 MW

ERCOT adds up each approved load's highest use in the month. It says this is how much approved load it believes is now operating. For scale, ERCOT set a September demand record of 86,647 MW on 12 September 2026.

Source: ERCOT: Monthly Operational Overview, September 2026 (opens in a new tab) Published 16 Oct 2026. Accessed 31 Oct 2026.

Utility pipelines, side by side

Each utility reports its pipeline on its own definition and date, so these cards are not a ranking and are never added up. How much each utility plans to spend on the grid is compared in US utility capex plans, and the nuclear and gas power producers signing deals with data centres (Constellation, Vistra, Talen) in power producers' Q3 2026 results.

Flag of United StatesProjected · Pipeline in contracting stages

over 54 GW

Dominion Energy (Virginia (PJM)): Data centre capacity in various stages of contracting, including over 12 GW under signed electric service agreements. Over 6 GW was added since the end of 2025 (13%). As of 30 Oct 2026.

Source: The Motley Fool: Dominion Energy (D) Q3 2026 earnings call transcript (opens in a new tab) Published 30 Oct 2026. Accessed 31 Oct 2026. Also: Dominion Energy: Dominion Energy Announces Third-Quarter 2026 Results (opens in a new tab) Published 30 Oct 2026. Accessed 31 Oct 2026.

AEP five-year capital plan: previous versus new (US$bn) Company plan

AEP's own plan as reported by Utility Dive from its third-quarter 2026 call on 28 October 2026. The new plan runs through 2031 and also includes about US$8bn for renewable energy. These are planned amounts, not money spent. AEP said the rise is driven by generation and transmission needed for contracted load, mostly data centres.

Source: Utility Dive: AEP increases investment plan 30% on generation, transmission spending (opens in a new tab) Published 29 Oct 2026. Accessed 31 Oct 2026.

Show the data as a table
Part of planPrevious planNew plan (Oct 2026)
Whole planUS$78bnUS$100bn
TransmissionUS$33bnUS$37bn
Gas-fired generationUS$13bnUS$20bn

New connection rules

Common questions

What are the PJM capacity auction results by year?

PJM pays power plants to be ready for peak demand. That price shot up after 2024/25 and has since hit the agreed ceiling.

Why it matters The price rose about elevenfold in four years.

  • 2024/25: around US$29 per MW per day
  • 2025/26: around US$270
  • 2026/27 to 2028/29: around US$325 to 333, at the cap

Source: PJM

How much does PJM's capacity auction cost?

About US$16bn a year for the next two years, up from around US$2bn.

Why it matters That is roughly seven times more, though PJM says it is not the full cost to households.

  • Around US$2.2bn (2024/25)
  • Around US$16.4bn (2027/28 and 2028/29)
  • Around US$30bn without the cap (simulation)

Source: PJM

How big is the ERCOT large load interconnection queue?

Huge. Requests to connect big users to the Texas grid reached around 474 GW, and about 9 in 10 are data centres.

Why it matters Only a fraction of these requests passed the first study.

  • Around 63 GW (December 2024)
  • Around 226 GW (November 2025)
  • Around 474 GW (June 2026)

Source: ERCOT

Why don't large-load requests turn into real demand?

Many requests are early bets. Developers apply for the same project in several places, before they have land, customers or money.

Why it matters In Texas, less than half the power approved for use was actually being drawn.

  • Around 9,500 MW approved
  • Around 4,100 MW actually used at peak (September 2026)

Source: ERCOT

How much electricity do US data centres use?

About 4 in every 100 units of US electricity in 2023, and that could double or triple by 2028.

Why it matters The 2028 figures are forecasts, not measurements.

  • 176 TWh (2023), about 4.4%
  • Forecast: 325 to 580 TWh (2028)

Source: Lawrence Berkeley National Laboratory

Which utilities have the most data centre load under contract?

Dominion, AEP and Southern Company report the most, but each counts differently, so it is not a ranking.

  • Dominion: over 54 GW in contract talks
  • AEP: around 84 GW contracted to 2031
  • Southern Company: around 17 GW contracted

Source: Company reports

Coverage limits: this page covers PJM and ERCOT in detail, CAISO's new rules, three utilities that publish data centre pipelines, and Alberta for comparison. MISO, SPP, the Southeast outside Southern Company, the West and New York are not yet covered. Company logos come from Wikimedia Commons and are shown for identification only. They do not imply endorsement, and CoolPower Index is vendor-neutral. Flags: flag-icons (MIT licence). Charts: Apache ECharts (Apache 2.0). This is not investment advice. Related: North America briefing · Power and water forecasts · Markets & Investment · United States market profile · Energy supply pathways.