Resources: energy

Energy supply pathways

How data centres get power, organised around delivery, firmness and timing. For each pathway: the evidence to ask for and the distinction that is most often blurred. There is no credible single best source for every country and facility.

JLL reported in January 2026 that the average wait for a grid connection in primary data centre markets exceeds four years, and that operators are turning to on-site power and battery storage (JLL 2026 outlook (opens in a new tab)).

Pathways

Energy supply pathways
PathwayEvidence to ask forImportant distinctionOn CoolPower Index
Grid connection and substationUtility queue and process, allocated capacity, connection date, flexibility terms and who pays for which works.A connection allocation is not commissioned IT load.Switchgear & Transformers suppliers, Data centre power distribution
Gas engines and turbinesPrime or standby duty, fuel supply, permits, derating, maintenance and evidence of delivered projects.Claims of fast procurement need current delivery and permitting evidence.Gensets & On-site Power suppliers
Diesel or HVO backup generationOperating duty, run-hour limits, engine maker approval of the fuel and fuel autonomy.Backup generation is not automatically continuous prime power.Gensets & On-site Power suppliers, Backup power and energy storage
Fuel cellsFuel and reforming, net output, start-up time, maintenance and project status.Fuel-cell chemistry does not by itself prove low-carbon supply.Gensets & On-site Power suppliers
Solar, wind and PPAsOn-site or off-site, resource profile, contract type, hourly matching and firming.Nameplate MW or annual certificates are not firm hourly supply.No portal record yet
Battery and long-duration storagePower (MW), usable energy (MWh), losses, reserves, degradation, dispatch and safety.Storage shifts energy. It is not an independent primary source.BESS & Energy Storage suppliers, Backup power and energy storage
Supply from existing nuclear plantsOperating or restart project, offtake milestones and the grid and regulatory context.Buying from an existing plant is different from new reactor delivery.No portal record yet
Small modular and advanced reactorsCountry, design, regulator, licence stage (construction or operation) and target dates.Permission to build is not permission to operate. No design is generically available now.No portal record yet
Geothermal and hydroLocal resource, project status, permitting and delivered-power terms.Availability and suitability are site-specific.No portal record yet

Keep these separate

These measure different things and should never be merged into one score:

  • Levelised cost of electricity (LCOE)
  • Delivered electricity tariff
  • Installed capital cost
  • Storage duration
  • Emissions accounting
  • Resilience

Project maturity should come from regulator or operator evidence. See projects and policy records for dated, sourced examples.

Sources

Gaps: U.S. NRC advanced reactor licensing milestones page returned HTTP 403 to our research tools on 18 October 2026, so it is not cited yet. Updated 18 Oct 2026.