Northern Virginia, Atlanta, Texas, the PJM grid, Alberta and Querétaro on one page. For engineers, buyers, consultants and investors. Every figure is dated, sourced and labelled Live, Confirmed or Projected.
North America in brief
The eight primary North American markets held a record 10,903 MW of data centre capacity in mid 2026, up 33.7% in a year, yet vacancy fell to a record low of 1.4% (CBRE).
Builders are racing: 7,481 MW was under construction in those markets, more than 80% already preleased, and Atlanta overtook Northern Virginia as the busiest construction market for the first time (CBRE).
US spending on data centre buildings reached an annual rate of US$85.0bn in August 2026, 73% more than a year earlier, and that excludes the servers inside (US Census Bureau).
Power is the bottleneck. Texas has paused new large data centre connections while ERCOT audits about 474 GW of requests, and Alberta's first 1,200 MW of grid room is fully allocated against about 19,565 MW asked for.
In the PJM grid that serves Northern Virginia, the capacity price has cleared at its cap for three auctions in a row, with data centres the main driver of the higher demand forecast (PJM, Market Monitor).
Mexico is small but growing: 279 MW installed nationally, 72% of it in Querétaro, with 181 MW under construction there (MEXDC).
Live
10,903 MW
capacity in the eight primary North American markets, mid 2026 (record)
Live running today or measured for a past period (inventory, vacancy, electricity use, construction spending, official statistics).
Confirmed signed, approved, allocated, auctioned or under construction. Not yet in service, or still being built.
Projected plans, connection requests, pipelines and forecasts. They can change or not happen.
Exact figure types used on this page
Official figure · Third-party estimate · Company statement · Under construction · Capacity auction result · Grid access granted, not built · Adopted policy or order · Connection requests · Forecast · Reported, not confirmed · Reported setback · Passed grid studies, not yet approved. Hover or tap a badge to see the exact type. Inventory (built capacity), capacity under construction, grid connection requests, electricity use and spending are different measures. They are never added together or drawn on the same axis. CBRE counts eight primary markets, not the whole of the US. MW is power, TWh is energy used over a year.
Where the capacity is, and where it is being built
Data centre capacity by primary market and state, mid 2026 (MW): partial coverage Live · Third-party estimate
Interactive chart loads here. The figures are also in the table below.
Inventory as CBRE measures it in its eight primary markets (Q2 2026 data). One source and one method, so the bars compare like for like. It is not the whole of the US, and capacity under construction is shown separately below, never added to these bars. Partial by design: this is the only state-level view on the page, and it uses this one source, so states outside CBRE's primary markets (for example Ohio or Iowa) do not appear.
Capacity under construction, selected markets, mid 2026 (MW) Confirmed · Under construction
Interactive chart loads here. The figures are also in the table below.
Under construction, not yet in service. CBRE gives a figure for these three markets on its public pages, out of 7,481.1 MW across all eight primary markets. Chicago has "more than 765 MW" under construction according to CBRE as reported by Data Center Frontier, so it is listed in the table only.
US spending on data centre buildings, monthly, at an annual rate (US$bn) Live · Official figure
Interactive chart loads here. The figures are also in the table below.
Value of private construction put in place for data centre buildings, seasonally adjusted annual rate. Census counts the building only, not servers, racks or IT equipment, and puts power plants and grid lines in a separate category. The latest month is preliminary and will be revised in the next two releases.
Each pair comes from one grid operator or government, so compare within a jurisdiction, not across them. Connection requests are not demand forecasts: many are speculative or duplicates. Dashed bars are projected, teal bars are confirmed.
Published forecasts, side by side Projected · Forecast
Each forecaster measures something different (energy used in a year, the increase in energy, capacity added), so they sit in a table, not on one chart. These are the forecasters' own figures with the date they were given. CoolPower Index makes no forecasts of its own.
Forecaster
What it measures
Forecast
Given
Source
Lawrence Berkeley National Laboratory for the US DOE
US data centre electricity use
325 to 580 TWh in 2028 (6.7% to 12% of US electricity), from 176 TWh in 2023 Scenario range
Record building, record-low vacancy, and power that cannot keep up.
Live · Third-party estimate
10,903 MW
Data centre capacity (inventory) across the eight primary North American markets, up 33.7% in a year. Net absorption was 1,456.2 MW in the half year. As of 30 Jun 2026.
Record-low vacancy across the primary markets, down from 1.6% a year earlier. Asking rents rose for every deployment size, led by 8.3% for 3 to 10 MW. As of 30 Jun 2026.
Under construction across the primary markets, a record, with 80.4% preleased. Less than 1,500 MW remains available, about six months of demand at the current pace. As of 30 Jun 2026.
Under construction in Atlanta, up 52.3% in a year. For the first time Atlanta overtook Northern Virginia as the top construction market in North America. As of 30 Jun 2026.
Spending on data centre buildings in August 2026 at a seasonally adjusted annual rate, up 73.2% from August 2025. Preliminary, excludes servers and racks. As of 2026-08.
Local moratoriums on data centres across the US, according to Axios, citing a survey of moratoria by Michael Bommarito. SemiAnalysis says a New York pause on environmental permits for larger sites has delayed nearly 1 GW. As of 31 Oct 2026.
Nvidia is reported to be in talks to guarantee debt financing for Nscale's West Virginia campus, where Anthropic has signed a US$44.6bn contract for the first building, according to Nscale's IPO filing. As of 30 Oct 2026.
Under construction in Northern Virginia, up 16.5%, slowed by land and permitting limits. All capacity due in 2026 is already committed. As of 30 Jun 2026.
PJM capacity price for June 2028 to May 2029, cleared at the cap across the whole region. The auction procured 138,317.8 MW but cleared 6,831.3 MW less than the reliability requirement. As of 14 Jul 2026.
Existing and forecast data centre load in the PJM load forecast behind the 2027/28 auction, including 13,018 MW of new or increased data centre load. As of 5 Jan 2026.
474 GW asked for, connections paused while the state audits them.
Projected · Connection requests
about 474 GW
Large-load interconnection requests in ERCOT, about 90% data centres, more than five times the record peak demand. Experts say much is speculative or duplicated. As of 5 Aug 2026.
Governor Abbott ordered an audit of data centres in the queue covering power, water and public subsidies. ERCOT aims to file its report by 10 December 2026, and its Batch Zero study will miss the 9 April 2027 date. As of 21 Aug 2026.
Peak demand of 17 large loads, mostly data centres, that have passed every ERCOT gate except approval to energise, ramping up over about five years. As of 21 Aug 2026.
Alberta rations grid room and puts projects that bring their own power first.
Coverage note: this section covers Alberta only. Quebec, Ontario, British Columbia and the rest of Canada are not yet covered, so these figures are not Canadian totals.
Projected · Connection requests
about 19,565 MW
New data centre load companies have asked to connect in Alberta, against a record provincial peak of about 12,800 MW. As of 30 Jul 2026.
Nobody counts them officially. One industry count finds around 11 GW in the eight biggest markets, led by Northern Virginia.
Why it matters US data centres used about 4 in every 100 units of the country's electricity in 2023.
Around 10,900 MW in 8 main markets (mid 2026)
Northern Virginia: around 4,500 MW
176 TWh, about 4.4% of US electricity (2023)
Source: CBRE, Lawrence Berkeley National Laboratory
Which US state has the most data centre capacity?
Virginia, thanks to Northern Virginia, the largest of the eight main markets. Georgia, Texas, Arizona and Illinois follow.
Why it matters These are city areas, not whole states, and smaller markets are left out.
Northern Virginia: around 4,500 MW
Atlanta: around 1,800 MW
Dallas-Fort Worth: around 1,400 MW
Phoenix: around 1,100 MW
Chicago: around 900 MW
Source: CBRE (mid 2026)
How much is being spent on US data centres?
Around US$85bn a year just on data centre buildings, up nearly three quarters in a year.
Why it matters The servers and chips inside cost much more, and are not in this figure.
Around US$85bn a year (August 2026)
Up 73% in a year
Source: US Census Bureau
Why has Texas paused new data centre connections?
Texas has not stopped connections, but its governor ordered a check on the huge queue of data centres asking for power.
Why it matters About 9 in every 10 big power requests in the queue are data centres.
Around 474 GW of large requests
Audit ordered: 3 August 2026
Report due: 10 December 2026
Source: Texas governor, ERCOT
Why are PJM capacity prices so high?
PJM runs a large part of the eastern US grid, and pays power plants to be ready for peak demand. Data centres pushed forecast demand up, so that price jumped about ninefold in one year.
Around US$29 per MW per day (2024/25)
Around US$270 (2025/26)
Then at the agreed cap for 3 years
Source: PJM, PJM Market Monitor
How much data centre capacity does Mexico have?
Around 280 MW, mostly in Querétaro.
Why it matters About 7 in every 10 megawatts in Mexico are in Querétaro.
Coverage limits: this briefing covers the eight CBRE primary markets, two US grids (PJM and ERCOT), Alberta in Canada and Mexico. Other US markets, Quebec, Ontario and British Columbia are not yet covered here. Company logos come from Wikimedia Commons or Simple Icons and are shown for identification only. They do not imply endorsement, and CoolPower Index is vendor-neutral. Flags: flag-icons (MIT licence). Charts: Apache ECharts (Apache 2.0). This is not investment advice. Other regions: Regions · Europe and UK · Asia Pacific · China · Compare markets.